PHOTO
Bulgartransgaz said it would use 461 million levs ($278 million) of the proceeds to make advance payments to Saudi-led group Arkad, which built the pipeline for 1.1 billion euros.
Gazprom’s export unit Gazprom Export has agreed to pay upfront for booked capacity from July 1, 2021 until June 30, 2023, Bulgartransgaz said in a statement.
Bulgaria’s 474 km gas pipeline, which transports Russian gas from its southern border with Turkey to its western border with Serbia — providing a link to the Russia-backed TurkStream twin pipeline to Serbia and Hungary, became operational in January.
The Bulgarian gas network operator will also use the money to cover 65 million euros in loans to commercial banks.
Bulgaria meets most of its gas needs with supplies from Gazprom.
Copyright: Arab News © 2021 All rights reserved. Provided by SyndiGate Media Inc. (Syndigate.info).