Dubai, UAE: HE Saeed Mohammed Al Tayer, MD & CEO of Dubai Electricity and Water Authority (DEWA), has reviewed the progress of the 300 megawatt (MW) second stage of the 800MW third phase of the Mohammed bin Rashid Al Maktoum Solar Park. The solar park is the largest single-site solar park in the world, based on the Independent Power Producer (IPP) model. It will generate 5,000MW by 2030 with investments of up to AED 50 billion.

During the visit, Al Tayer was accompanied by Waleed Salman, Executive Vice President of Business Development & Excellence at DEWA; Jamal Shaheen Al Hammadi, Vice President of Clean Energy & Diversification at DEWA; and other DEWA staff.

DEWA is building the 800MW third phase of the solar park using photovoltaic technology in three stages, in partnership with a consortium led by Abu Dhabi Future Energy Company (Masdar) and EDF Group, through its subsidiary EDF Énergies Nouvelles. This solar plant is the first of its kind in the Middle East and North Africa, with an advanced solar tracking system to increase generation efficiency by 20-30% when compared to fixed installations. DEWA recorded a world record in the cost of photovoltaic solar power for this phase of the solar park, at a Levelised Cost of Energy (LCOE) of USD 2.99 cents per kilowatthour, using photovoltaic solar panels.

Al Tayer was briefed on the progress of the 300MW second phase of the solar park, which will be operational in late June. Construction of the 300MW third stage started earlier this year and will be operational in 2020.

The first stage has a capacity of 200MW and became operational in May 2018. It uses unique technologies, including over 800,000 self-cleaning solar cells that use robots to maintain efficiency. This stage provides over 60,000 residences with electricity, reducing over 270,000 tonnes of carbon emissions every year. DEWA established Shuaa Energy 2 with a 60% stake in the company in partnership with the Masdar-led consortium, and Électricité de France (EDF), through its subsidiary EDF Énergies Nouvelles. The consortium owns the remaining 40% of the company; Masdar owns 24% and EDF Énergies Nouvelles owns 16%. The international consortium led by the renewable energy contractors GranSolar and Acciona from Spain and Ghella from Italy are handling the engineering, procurement, and construction (EPC).

The 13MW photovoltaic first phase of the Mohammed bin Rashid Al Maktoum Solar Park became operational in 2013. The 200MW photovoltaic second phase of the solar park was launched in March 2017, and the 800MW photovoltaic third phase will be operational by 2020.The fourth phase of the solar park is the largest single-site solar IPP project in the world and combines CSP and photovoltaic technology. The phase will use hybrid technologies to produce 950MW of clean energy.

DEWA issued a Request for Qualification (RFQ) for developers to build and operate the fifth phase of the solar park with a capacity of 900MW. The phase will use photovoltaic solar panels based on the IPP model and will be commissioned in stages from Q2 2021.

-Ends-

For more information, please contact:
Ribal Dayekh / Ahmed Albanna                                             
Dubai Electricity and Water Authority                               
+971 4 322 2405 / +971 55 22 67222                              
ribal.dayekh@dewa.gov.ae                                                          
ahmed.albanna@dewa.gov.ae                                          

Joumana El Tarabulsi / Antoine Boghos
Publinet
+971 58 2221631 / +971 50 3310001
joumana@cbpr.me
antoine@cbpr.me

© Press Release 2019

Disclaimer: The contents of this press release was provided from an external third party provider. This website is not responsible for, and does not control, such external content. This content is provided on an “as is” and “as available” basis and has not been edited in any way. Neither this website nor our affiliates guarantee the accuracy of or endorse the views or opinions expressed in this press release.

The press release is provided for informational purposes only. The content does not provide tax, legal or investment advice or opinion regarding the suitability, value or profitability of any particular security, portfolio or investment strategy. Neither this website nor our affiliates shall be liable for any errors or inaccuracies in the content, or for any actions taken by you in reliance thereon. You expressly agree that your use of the information within this article is at your sole risk.

To the fullest extent permitted by applicable law, this website, its parent company, its subsidiaries, its affiliates and the respective shareholders, directors, officers, employees, agents, advertisers, content providers and licensors will not be liable (jointly or severally) to you for any direct, indirect, consequential, special, incidental, punitive or exemplary damages, including without limitation, lost profits, lost savings and lost revenues, whether in negligence, tort, contract or any other theory of liability, even if the parties have been advised of the possibility or could have foreseen any such damages.