Mar 30 2009 |
more articles from
|
Scrapped Kuwait refinery project could be saved
Monday, Mar 30, 2009
Gulf News
A few days ago, Kuwait announced it was halting all works related to Al Zour refinery project, which was supposed to be the largest refinery in the region at 615,000 barrels a day (bpd).
The reason given for this decision is that an "independent watchdog had decided it was not feasible" and that the procedure of awards was not in complete adherence to tender regulations. Apparently there were even some questions by members of parliament about the viability of the project and the procedures as well.
The project was originally announced in 2005 and at that time Kuwait's refining capacity was close to 900,000 bpd, ample for its modest domestic requirement with a large surplus for export.
Building such a large and complex refinery in one go was for me too good to be true as the task was enormous in cost and logistics. However, planners must have been encouraged at the time because of the severe shortage of refining capacity worldwide, which was one of the main reasons for the rise in crude oil prices and the appreciation of refinery profit margins in the last few years.
Much work was put into this project including initial studies and the refinery was supposed to cost over $6 billion and to start operations by 2012.
But the rush everywhere for oil and gas expansion and refining projects regionally and worldwide has driven the cost madly upward to the unwarranted level of about $15 billion.
The cancellation therefore is an unavoidable shock to the Kuwait National Petroleum Company (KNPC) and to all the contractors involved after a substantial amount of money, around $1 billion, was spent on the project.
In retrospect, one would ask, why such a large capacity in one go? Why could the refinery not be built in stages to reduce the risk of rising cost and delays?
Why didn't the government stop the process in time when there were reports back in 2007 saying that the project was infeasible and that it would bring negative returns?
In my view there may be a way back to the project in one form or another after reconsideration of the size and process configuration, especially now that KNPC wants somehow to phase out Shauiba Refinery, the oldest in Kuwait. This may take some time but KNPC must be longing to salvage some of its expenditure by using some of the work already completed and the process licences already paid for. Lower prices for engineering contracts are now expected due to the curtailment of investment and the world recession. Contractors may soon be hungry for work and offer Kuwait a better deal.
In the meantime the world has moved on as the refining capacity increased by about 3 million bpd between 2005 and the end of 2008 even though a lot of small and old refineries were phased out.
Some additional capacity will undoubtedly come on stream in Saudi Arabia where some two grassroots refineries are under construction or design in addition to the expansion and modernisation of the older refineries.
Other regions in Asia are also witnessing expansion to cater for future demand and to improve products' quality for environmental and efficiency reasons.
The cancellation of the Kuwait project may turn out to be advantageous to its competitors and may somehow be a support for the future refinery margins.
- The writer is a former Head of Energy Studies Department at the Opec Secretariat.
© Gulf News 2009. All rights reserved.
Zawya Comment Policy
-
Zawya encourages you to add a comment to this discussion. You agree that when you add content to this discussion your comments will not:
1.1 Contain any material which is libelous or defamatory of any person, is obscene, offensive, hateful or inflammatory or causes damage to the reputation of any person or organisation.
1.2 Promote sexually explicit material, violence, discrimination based on race, sex, religion, nationality, disability, sexual orientation or age or any illegal activity.
1.3 Be made in breach of any legal duty owed to a third party, such as a contractual duty or a duty of confidence.
1.4 Be threatening, abuse or invade another's privacy, or cause annoyance, inconvenience or needless anxiety.
1.5 Be used to impersonate any person, to misrepresent your identity or affiliation with any person, or be likely to deceive any person.
1.6 Give the impression that they represent Zawya.
1.7 Advocate, promote or assist any unlawful act such as (by way of example only) copyright infringement or computer misuse. - The content posted on www.zawya.com is created by members of the public. The views expressed are theirs and unless specifically stated are not those of Zawya. Zawya reserves the right to review all comments prior to posting and edit or delete any contribution, but Zawya is not responsible for and can not be held liable for any content posted by members of the public on www.zawya.com.
- Zawya is not responsible for the availability or content of any third party sites that are accessible through www.zawya.com. Any links to third party websites from www.zawya.com do not amount to any endorsement of that site by Zawya and any use of that site by you is at your own risk.
- By submitting your comment, you hereby give Zawya the right, but not the obligation, to post, air, edit, exhibit, telecast, webcast, re-use, publish, reproduce, use, license, print, distribute or otherwise use your comments worldwide, in perpetuity.
Copyright © 2012 Zawya Ltd. All rights reserved. |
provided by www.zawya.com |



Post Your Comment