Dubai, UAE: HE Saeed Mohammed Al Tayer, MD & CEO of Dubai Electricity and Water Authority (DEWA), has today announced that the consortium led by ACWA Power and Gulf Investment Corporation is the Preferred Bidder to build and operate the 900MW 5th phase of the Mohammed bin Rashid Al Maktoum Solar Park for using photovoltaic (PV) solar panels based on the Independent Power Producer (IPP) model.

DEWA has achieved a world record by receiving the lowest bid of USD 1.6953 cents per kilowatt hour (kW/h) for this phase. DEWA has released the tender for the 5th phase in February 2019, and received 60 Requests for Qualifications (RFQ).

“We are striving to achieve the vision of His Highness Sheikh Mohammed bin Rashid Al Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, to transform Dubai into a global hub for clean energy and green economy. We also support the Dubai Clean Energy Strategy 2050 to provide 75% of Dubai’s total power output from clean energy by 2050 and make Dubai the city with the lowest carbon footprint in the world. To achieve this, DEWA launched several leading renewable projects, including the Mohammed bin Rashid Al Maktoum Solar Park, the largest single-site solar park in the world. Using the Independent Power Producer (IPP) model, it will have a capacity of 5,000MW by 2030 with investments totaling AED 50 billion,” said HE Saeed Mohammed Al Tayer.

“The 900MW 5th phase of the solar park using PV solar panels based on the IPP model will become operational in stages starting Q2 of 2021. The project documents, Power Purchase Agreement (PPA), and financial close agreements will be signed in due course,” added Al Tayer.

The projects at the Mohammed bin Rashid Al Maktoum Solar Park, the largest single-site solar park in the world, are of great interest to international developers and reaffirms investor confidence in the major projects that are supported by the Government of Dubai. DEWA has attracted huge investments to the UAE from the private sector and foreign banks, leading to increased cash flow to the economy of Dubai and the UAE. The Current total production capacity of solar projects at the solar park is 713MW. DEWA is building three other projects with a total capacity of 1,250MW. The 900MW 5th phase of the solar park will increase the production capacity to 2,863MW.

© Press Release 2019

Disclaimer: The contents of this press release was provided from an external third party provider. This website is not responsible for, and does not control, such external content. This content is provided on an “as is” and “as available” basis and has not been edited in any way. Neither this website nor our affiliates guarantee the accuracy of or endorse the views or opinions expressed in this press release.

The press release is provided for informational purposes only. The content does not provide tax, legal or investment advice or opinion regarding the suitability, value or profitability of any particular security, portfolio or investment strategy. Neither this website nor our affiliates shall be liable for any errors or inaccuracies in the content, or for any actions taken by you in reliance thereon. You expressly agree that your use of the information within this article is at your sole risk.

To the fullest extent permitted by applicable law, this website, its parent company, its subsidiaries, its affiliates and the respective shareholders, directors, officers, employees, agents, advertisers, content providers and licensors will not be liable (jointly or severally) to you for any direct, indirect, consequential, special, incidental, punitive or exemplary damages, including without limitation, lost profits, lost savings and lost revenues, whether in negligence, tort, contract or any other theory of liability, even if the parties have been advised of the possibility or could have foreseen any such damages.