Mammoet has loaded out a main support frame (MSF) module in Thailand, using a significant 604 axle lines of SPMT at Aibel Thailand’s yard in Leam Chabang. This module was the largest ever fabricated by Aibel Thailand and the largest to be loaded-out in Thailand using SPMTs. The mega MSF module weighed approximately 14,500t, and at 16,258t with grillage.

As Mammoet has worked closely with Aibel Thailand in the last decade, assisting Aibel in almost all of their heavy transportation work, Mammoet was once again selected as the trusted partner to perform this record-breaking module transportation.

Mammoet’s global network of engineering expertise meant that it was able to provide Aibel with a project team made up of professionals from all over the world. The team included specialists from Thailand and Mammoet’s Global Offshore Services division, who were in charge of weighing the module, while mechanics and supervisors from Australia, Malaysia, Netherlands and Thailand covered the site move and load-out execution using the SPMT trailers.

The 604 axle lines of SPMT and 21 PPUs were sourced from various depots in Asia-Pacific, Africa and the Middle East. It was a logistical challenge for the team to bring in such a significant number of SPMTs from different locations due to COVID-19 restrictions, which complicated shipping schedules. Nonetheless, all equipment was mobilized on time, and all trailers were assembled weeks before the load-out took place. The team’s strong technical expertise ensured all axle-lines functioned together and are ready on time.

On site, weighing of the MSF module was completed using Mammoet’s weighing system swiftly; within a day. Once the load cells were removed, the SPMT trailers were driven in position under the MSF module.

With the SPMTs in position and the hydraulic and electronic systems connected, the module was lifted up from the fabrication supports using the SPMTs’ suspension systems. The site move covered approximately 700m in distance to the load out quay, and it was completed the day before the load out onto the vessel took place.

The following day, Mammoet, Aibel and the crew of the vessel coordinated well to ensure load-out of this module went smoothly onto the ship. It took a few hours before the module was rolled onto the vessel and accurately aligned with the grillage.

Shimming and adjusting procedures were undertaken before the MSF module could be completely set down on the vessel. After this, the SPMT trailers were removed from underneath the module.

The mega MSF module has since been shipped to Norway and is now part of Equinor’s fifth platform for the Johan Sverdrup oil field. The oil field is expected to have a daily production capacity of up to 535,000 barrels by the end of this year.

-Ends-

Mammoet

Mammoet helps clients with Smarter, Safer and Stronger solutions to any heavy lifting or transport challenge. We aim to develop long term relationships in order to understand their businesses and challenges best, so we can realize the most efficient and cost-effective approaches. We have a unique global network and an unparalleled fleet of equipment. Through deep and longstanding engineering expertise and the highest quality and safety standards in execution we bring an intelligent and flexible approach to projects across a wide breadth of industry sectors. Clients trust us to help them achieve feats that were once considered impossible, and we have often broken records in doing so.

www.mammoet.com 

For more information on the above story, please contact:
Mammoet
Denise Chiew
MarCom Specialist (APAC)
denise.chiew@mammoet.com

Despite logistical challenges brought about due to COVID-19 restrictions, the team ensured all 604 axle lines were mobilized and connected weeks before the load-out took place.

Strong coordination amongst Mammoet, Aibel and various other stakeholders were required for the load-out of this module onto the ship.

Send us your press releases to pressrelease.zawya@refinitiv.com

© Press Release 2021

Disclaimer: The contents of this press release was provided from an external third party provider. This website is not responsible for, and does not control, such external content. This content is provided on an “as is” and “as available” basis and has not been edited in any way. Neither this website nor our affiliates guarantee the accuracy of or endorse the views or opinions expressed in this press release.

The press release is provided for informational purposes only. The content does not provide tax, legal or investment advice or opinion regarding the suitability, value or profitability of any particular security, portfolio or investment strategy. Neither this website nor our affiliates shall be liable for any errors or inaccuracies in the content, or for any actions taken by you in reliance thereon. You expressly agree that your use of the information within this article is at your sole risk.

To the fullest extent permitted by applicable law, this website, its parent company, its subsidiaries, its affiliates and the respective shareholders, directors, officers, employees, agents, advertisers, content providers and licensors will not be liable (jointly or severally) to you for any direct, indirect, consequential, special, incidental, punitive or exemplary damages, including without limitation, lost profits, lost savings and lost revenues, whether in negligence, tort, contract or any other theory of liability, even if the parties have been advised of the possibility or could have foreseen any such damages.