Dec 05 2011 |
more articles from
|
Saudi Arabia's Qurayyah power plant project gathers pace
RIYADH: A consortium, led by ACWA Power (a 100 percent Saudi-owned company), recently issued notice to proceed with the construction of the largest independent power generation project in the world, Qurayyah Independent Power Project (IPP).The project, to be developed on a BOO (build, own, operate) basis, will be located at Qurayyah, on the eastern coast of Saudi Arabia adjacent to existing SEC facilities.
The project, the third of its type, and the largest IPP being developed by SEC, represents another major development in the Saudi power sector to help meet the rapidly increasing power demand in Saudi Arabia.
The project company -- Hajr Electricity Production Company (Hajr) -- was established with the winning consortium owning 50 percent and SEC owning the remaining 50 percent.
Yousef Al-Ouhali, executive managing officer of the Hajr, said: "Qurayyah IPP is a greenfield independent power project with a net generation capacity of 3927 MW. The design production capacity will make it the largest IPP combine cycle gas-fired power plant in the world once completed".
The project is being funded with $730 million of equity capital funded through an equity bridge Murabaha facility provided by Arab National Bank , Banque Saudi Fransi , The National Commercial Bank, Samba Capital, Saudi British Bank, and Saudi Hollandi Bank and 2,075 million of debt funded by Arab National Bank , Banque Saudi Fransi , Hong-Kong Shanghai Bank, Korea Export Import Bank, Kreditanstalt Fur Wideraufbau, The National Commercial Bank, Samba Capital, Saudi British Bank, Standard Chartered Bank, Sumitomo Mitsui Banking Corporation and US Export Import Bank.
Qurayyah IPP comprises six identical groups of equipment, each delivering net output of 654.5 MW.
Each group comprises two gas turbines (GTS), two heat recovery steam generators (HRSG) and one steam turbine.
The Qurayyah IPP Plant is designed and will be constructed to comply with all applicable environmental laws, guidelines, regulations and standards set by World Bank, IFC and Saudi Presidency of Meteorology and Environment (PME).
Siemens will provide all major equipment and electrical systems and Samsung C&T will Engineer, Procure and Construct the project as the EPC contractor to deliver the project.
Once completed, the plant will be operated by The First National Operation & Maintenance Company (NOMAC) a subsidiary of ACWA Power under a long-term operation and maintenance contract with Siemens providing parts and services for the gas turbines under a long-term service Agreement (LTSA) with NOMAC.
Al-Ouhali said: "We are proud to be the project owner of Qurayyah IPP not only because it is the world's largest combined cycle IPP, but most importantly the project will provide major economic advantage for Saudi Arabia."
He added: "First: The project was bid with the lowest tariff possible (21 percent lower than the nearest bidder), thus delivering over SR2 billion of savings over 20 years to the economy of the Kingdom. Second: The project is designed with the highest thermal performance possible, more than 52 percent efficiency, or 14 percent more efficient than the traditional steam power plant exist in the Kingdom now, which makes it the most efficient in Saudi Arabia. This high efficiency will save the Kingdom more than SR2 million per day in fuel cost, using the present world natural gas price. Third: This high efficiency will also save the Kingdom's natural resources, as the project will save more than 160 million cubic feet of natural gas per day of equivalent MW production."
The Qurayyah IPP plant is designed and will be constructed to comply with all applicable environmental laws, guidelines, regulations and standards as per World Bank, IFC and Saudi Presidency of Meteorology and Environment (PME).
The project will substantially increase power supplies to the Saudi power grid.
© Arab News 2011
Zawya Comment Policy
-
Zawya encourages you to add a comment to this discussion. You agree that when you add content to this discussion your comments will not:
1.1 Contain any material which is libelous or defamatory of any person, is obscene, offensive, hateful or inflammatory or causes damage to the reputation of any person or organisation.
1.2 Promote sexually explicit material, violence, discrimination based on race, sex, religion, nationality, disability, sexual orientation or age or any illegal activity.
1.3 Be made in breach of any legal duty owed to a third party, such as a contractual duty or a duty of confidence.
1.4 Be threatening, abuse or invade another's privacy, or cause annoyance, inconvenience or needless anxiety.
1.5 Be used to impersonate any person, to misrepresent your identity or affiliation with any person, or be likely to deceive any person.
1.6 Give the impression that they represent Zawya.
1.7 Advocate, promote or assist any unlawful act such as (by way of example only) copyright infringement or computer misuse. - The content posted on www.zawya.com is created by members of the public. The views expressed are theirs and unless specifically stated are not those of Zawya. Zawya reserves the right to review all comments prior to posting and edit or delete any contribution, but Zawya is not responsible for and can not be held liable for any content posted by members of the public on www.zawya.com.
- Zawya is not responsible for the availability or content of any third party sites that are accessible through www.zawya.com. Any links to third party websites from www.zawya.com do not amount to any endorsement of that site by Zawya and any use of that site by you is at your own risk.
- By submitting your comment, you hereby give Zawya the right, but not the obligation, to post, air, edit, exhibit, telecast, webcast, re-use, publish, reproduce, use, license, print, distribute or otherwise use your comments worldwide, in perpetuity.
Copyright © 2012 Zawya Ltd. All rights reserved. |
provided by www.zawya.com |



Post Your Comment