Bemco signs SR2.145bn loan deal with BSF, NCB
- Text size
JEDDAH: Banque Saudi FransiBanque Saudi Fransi
(BSFBSF
) and National Commercial BankNational Commercial Bank
(NCBNCB
), both mandated lead arrangers, concluded the signing of a SR2.145 billion contract financing facility on Tuesday for Arabian Bemco Contracting CompanyArabian Bemco Contracting Company
Ltd., a lead regional engineering contractor for building power plants and industrial and infrastructure projects.The NCBNCB
is also acting as the issuing bank, facility agent and security agent.
Arabian BemcoArabian Bemco
's CEO Henry Sarkissian, NCBNCB
's Vice President and Chief Corporate Banker Mansour A. Al-Saghayer as well as BSFBSF
's Regional Corporate Banking Group Head Mutasim N. Mufti jointly signed the deal at the Qasr Al-Sharq hotel.
The deal follows the award of a contract to the consortium, led by Arabian BemcoArabian Bemco
with Doosan Heavy Industries, to convert the Qurayyah Power Plant from an open cycle process to one of a combined cycle.
Under the agreement, the consortium will build additional capacity for the existing plant, with work in its final stages. Total capacity will be raised from 2,000 MW to 3,200 MW.
Sarkissian expressed his appreciation for the confidence of the banks. "This reflects their confidence in BemcoBemco
's performance abilities, and its shareholders and management. It also demonstrates the financial strength and commitment of Arabian BemcoArabian Bemco
's partners and management to meet its obligations toward the lenders and the clients," he said.
The company, Sarkisian added, intends to expand its activities soon to include the rest of the GCC, Africa and Eastern countries not only in the construction sector, but also in the area of investment and development of infrastructure projects.
"Arabian BemcoArabian Bemco
's partners have also expressed their intention to convert part of its ownership into a public company soon," he said.
Ghassan Y. Basna, Arabian BemcoArabian Bemco
's vice president for finance, told Arab News that the financing for Qurayyah Power Plant is for the second phase of work.
The contract from the Saudi Electricity Company (SEC) for the plant was awarded on Sept. 16, 2009. It consists of five power blocks to be completed between May 2012 and January 2013. The SEC has recently raised SR7 billion through the issuance of sukuks to fund the project, he added.
© Arab News 2010
Zawya is a distributor (and not a publisher) of content supplied by third parties and subscribers. Any opinions, advice, statements, services, offers, or other information or content expressed or made available by those third parties, including information providers, subscribers or other users of the Service, are those of the respective author(s) or distributor(s) and not of the Company. The Company neither endorses nor is responsible for the accuracy or reliability of any opinion, advice or statement made on the Service by anyone other than authorized Service employee spokespersons while acting in their official capacities. The Company is not responsible for any infringement of intellectual property rights or breach of any applicable law or regulation, including regulation in relation to financial services or the distribution of financial products, defamation, data protection, telecommunications (including regulations relating to excessive use, spamming or other abusive activities) or obscene, offensive or illegal content). Under no circumstances will the Company be liable for any loss or damage caused by a member's reliance on information obtained through the Service. It is the responsibility of member to evaluate the accuracy, completeness or usefulness of any information, opinion, advice or other content available through the Service. Please seek the advice of professionals, as appropriate, regarding the evaluation of any specific information, opinion, advice or other content.
Read the full Member Agreement
http://www.zawya.com/legal/NewsLetter.cfm?name=disclaimer







Loading ...
Post a Comment
1.1 Contain any material which is libelous or defamatory of any person, is obscene, offensive, hateful or inflammatory or causes damage to the reputation of any person or organisation.
1.2 Promote sexually explicit material, violence, discrimination based on race, sex, religion, nationality, disability, sexual orientation or age or any illegal activity.
1.3 Be made in breach of any legal duty owed to a third party, such as a contractual duty or a duty of confidence.
1.4 Be threatening, abuse or invade another's privacy, or cause annoyance, inconvenience or needless anxiety.
1.5 Be used to impersonate any person, to misrepresent your identity or affiliation with any person, or be likely to deceive any person.
1.6 Give the impression that they represent Zawya.
1.7 Advocate, promote or assist any unlawful act such as (by way of example only) copyright infringement or computer misuse.