25 Dec 2009 Arab News
 

SR1bn loss due to delays in sewage project

  • Text size
  •  
  •  

MAKKAH: Officials in charge of executing the project of the sewage network in Jeddah, which was approved for implementation in 2005, have committed administrative and financial violations of close to SR1 billion, causing delays in the completion of the project that should have finished within three years, the General Auditing Bureau said in a recent report.

"These violations were behind the delay in the execution of a sewage network in the central and northern districts of Jeddah," the report said.

According to the report, the general budget of the state has incurred losses of hundreds of millions of riyals because of the delay in the implementation of the project.

"Many years have passed since the beginning of work in the project without the officials being able to finish it or execute the high orders regarding it," the report said.

The report recalled that the government had earmarked SR6.6 billion for a sewage network covering all districts and residential areas in Jeddah.

"This is the highest budget for a sewage system in any city in the Kingdom including Riyadh," it added.

The report said the contractor was unable to implement the work stipulated in the contract regarding the quantities and the timeframe proposed by him before the signing of the contract.

"The contractor has recorded the delays of 26 months judged by the accomplishment rates he had registered during the first 10 months of the duration of the contract," it said.

Based on the report of the consultant monitoring the execution of the project, which was the Saudi Ittihad Engineering Company, the General Auditing Bureau attributed the delay to the inability of the contractor to provide enough manpower and equipment. The bureau also indicated its unhappiness over the extension of the contract by a further 13 months by the Ministry of WaterMinistry of WaterLoading... under the request of the contractor.

"This has incurred losses of about SR19 million on the state budget," it added.

The report noted that the contractor was neither fined or punished for his delays and said his justifications for the extension of the tenure of the contract were not realistic and were contrary to the monthly accomplishment reports submitted by the monitoring consultant.

The report also said the confidence of the Ministry of WaterMinistry of WaterLoading... in the contractor was the main reason behind the delay in the execution of the project.

It said the Ministry of Finance had proposed to the chief of the office of the Cabinet, before the signing of the contract, to make its duration at least five years because of the large size of the project and the substantial amount of money allotted for it but the Ministry of WaterMinistry of WaterLoading... refused this on the ground that the executing company was a specialized one, very qualified in executing sewage schemes and had the ability and experience to finish the project within three years.

The report said in its justification to make the duration of the contract three years, the Ministry of WaterMinistry of WaterLoading... warned that any delay beyond this time might cost the government millions of riyals annually because of the rise of the level of the surface water that might damage ground services and the buildings.

The General Auditing Bureau issued its report after random field visits to the sewage projects and a series of meetings with the monitoring consultant, representatives of the contractor and the department of water in Jeddah.

It presented its recommendations regarding the project which, among others, included the reviewing of the extension given to the contractor because he had violated the rules of extensions embodied in the government's purchases regulations and because the approvals for the extension were based on unrealistic data that ignored the mistakes of the contractor and his inability to execute the project on time.

The bureau recommended that the project be implemented in its original time of 36 months, the contractor be fined for the delays and also be made to incur expenses of any additional construction work.

The General Auditing Bureau called for the formation of an investigation committee comprising representatives of the Ministry of WaterMinistry of WaterLoading... and the directorate general of water in Makkah to question those responsible for the extension of the duration of the project. It suggested that based on the results of the investigation, a technical committee should be formed to check all the other items of the contract to see if they were in line with the government rules of purchases.

© Arab News 2009

x DISCLAIMER

Zawya is a distributor (and not a publisher) of content supplied by third parties and subscribers. Any opinions, advice, statements, services, offers, or other information or content expressed or made available by those third parties, including information providers, subscribers or other users of the Service, are those of the respective author(s) or distributor(s) and not of the Company. The Company neither endorses nor is responsible for the accuracy or reliability of any opinion, advice or statement made on the Service by anyone other than authorized Service employee spokespersons while acting in their official capacities. The Company is not responsible for any infringement of intellectual property rights or breach of any applicable law or regulation, including regulation in relation to financial services or the distribution of financial products, defamation, data protection, telecommunications (including regulations relating to excessive use, spamming or other abusive activities) or obscene, offensive or illegal content). Under no circumstances will the Company be liable for any loss or damage caused by a member's reliance on information obtained through the Service. It is the responsibility of member to evaluate the accuracy, completeness or usefulness of any information, opinion, advice or other content available through the Service. Please seek the advice of professionals, as appropriate, regarding the evaluation of any specific information, opinion, advice or other content.

Read the full Member Agreement
http://www.zawya.com/legal/NewsLetter.cfm?name=disclaimer
Access to this article is subject to specific terms and condition.
 
 

Post a Comment

 
  • Comment Title (optional)
  • Express your views or tell us more about this article
  • First Name
  • Last Name
  • Email Address
  • Company Name (optional)
Leave this field empty
 
 
Zawya Comment Policy
 
  1. Zawya encourages you to add a comment to this discussion. You agree that when you add content to this discussion your comments will not:
    1.1   Contain any material which is libelous or defamatory of any person, is obscene, offensive, hateful or inflammatory or causes damage to the reputation of any person or organisation.
    1.2   Promote sexually explicit material, violence, discrimination based on race, sex, religion, nationality, disability, sexual orientation or age or any illegal activity.
    1.3   Be made in breach of any legal duty owed to a third party, such as a contractual duty or a duty of confidence.
    1.4   Be threatening, abuse or invade another's privacy, or cause annoyance, inconvenience or needless anxiety.
    1.5   Be used to impersonate any person, to misrepresent your identity or affiliation with any person, or be likely to deceive any person.
    1.6   Give the impression that they represent Zawya.
    1.7   Advocate, promote or assist any unlawful act such as (by way of example only) copyright infringement or computer misuse.
  2. The content posted on www.zawya.com is created by members of the public. The views expressed are theirs and unless specifically stated are not those of Zawya. Zawya reserves the right to review all comments prior to posting and edit or delete any contribution, but Zawya is not responsible for and can not be held liable for any content posted by members of the public on www.zawya.com.
  3. Zawya is not responsible for the availability or content of any third party sites that are accessible through www.zawya.com. Any links to third party websites from www.zawya.com do not amount to any endorsement of that site by Zawya and any use of that site by you is at your own risk.
  4. By submitting your comment, you hereby give Zawya the right, but not the obligation, to post, air, edit, exhibit, telecast, webcast, re-use, publish, reproduce, use, license, print, distribute or otherwise use your comments worldwide, in perpetuity.