| Background |
Abu Dhabi Sewerage Services Company (ADSSC)Abu Dhabi Sewerage Services Company (ADSSC) plans to construct the first package of the deep sewer tunnel running from the northern part of Abu Dhabi Island to the mainland. The project aims to replace some of the existing pumping stations in Abu Dhabi and will decrease the pressure on the existing system. The project includes the construction of a 16.2 Km tunnel length with a 4 m diameter. This package (T01) is one of the three packages making up the deep tunnel sewer linking the northern part of Abu Dhabi Island to the mainland. The deep sewer tunnel will have a total lenght of 42 km long. The 2 other packages include the construction of a sewer tunnel from the Mussafah area to Mafraq (T01) and a sewer tunnel from Mafraq to Al Wathba (T03). The deep sewer tunnel is part of a bigger program, the Strategic Tunnel Enhancement Programme (STEP) implemented by ADSSC to handle the increasing volumes of waste management in Abu Dhabi. CH2M HillCH2M Hill is the PMC. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q3 2012 |
DB | Design of the project is expected to be completed | | Q1 2013 | DB | Excavation works expected to be completed | | Q1 2013 | DB | Layering of the tunnel is expected to start | | Nov 2013 | DB | Project expected to be completed
|
|
| Latest Events |
In March 2012, excavation works started. In Q3 2012, design of the the project is expected to be completed. In Q1 2013, excavation works are expected to be completed and tunnel layering is expected to start. In Q4 2013, the project is expected to be completed. |
| Previous Events |
In December 2011, preliminary works were completed. In July 2011, preliminary and excavation works were ongoing. In April 2011, the preliminary and excavation works started. In February 2011, the DB contract T01 was awarded to Samsung CorporationSamsung Corporation . On 23 April 2009, bidders submitted their proposals for the DB contract T01. At the end of January 2009, the ITB for the DB contract T01 was issued. In September 2008, bidders submitted their pre-qualification applications. On 17 August 2008, the RFQ for the DB contract was issued. In February 2008, the PMC contract was awarded to CH2M HillCH2M Hill . In 2007, the project was announced. |
| Scope of Work |
Construction of a deep sewer tunnel of 16.2 Km length and a 4 m diameter. |
| Contract Packages |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2007 |
Planning | Project announced
|
| Feb 2008 |
PMC | Contract awarded to CH2M HillCH2M Hill
|
| 17 Aug 2008 |
DB | RFQ issued
|
| Sep 2008 |
DB | Deadline for the submission of prequalification applications
|
| Jan 2009 |
DB | ITB for the second DB contract issued (tunnel from Abu Dhabi island to the mainland - T01)
|
| 23 Apr 2009 |
DB | Bidders submitted their proposals for T01
|
| Q1 2011 |
DB | DB contracts T01 awarded to Samsung CorporationSamsung Corporation
- Hyundai Engineering and Construction Company
- Lindenberg-Emirates
- McConnell Dowell
- Odebrecht
- Samsung Corporation
- Vinci Grand Projets
|
- McConnell Dowell
- Odebrecht
- Samsung Corporation
|
|
|
| Apr 2011 |
DB | Preliminary and excavation works started
|
| Dec 2011 |
DB | Preliminary works completed
|
| Q3 2012 |
DB | Design of the project is expected to be completed
|
| Q1 2013 |
DB | Excavation works expected to be completed | | | DB | Layering of the tunnel is expected to start
|
| Nov 2013 |
DB | Project expected to be completed
|
|
|