| Also Known As |
: |
SEHA |
| Country |
: |
UAE |
| Project Value |
: |
USD 708,000,000 Estimated |
| Sector |
: |
Real Estate | Healthcare |
|
Consultant |
: |
Jv of ACME Healthcare Consultancy, Faust Consult Architects and Engineers and Obermeyer Engineering Consulting
(Design) |
|
PMC |
: |
Allen and Shariff International
|
|
Contractors |
: |
Strabag
(Enablig works) |
Ed Zueblin
(Construction) |
| Profile Type |
: |
Standalone Project
|
|
Phase: Construction - Execution
|
|
Completion: 2013
|
|
|
|
| Background |
The Abu Dhabi Health Service CompanyAbu Dhabi Health Service Company plans to build Al Ain Hospital located in Abu Dhabi. Al Ain Hospital will spread over an area of 358,000 sq. m. and will include 688 beds and 1500 car parking. The JV of ICME Healthcare, Faust Consult Architects and Engineers and Obermeyer Engineering Consulting is the design consultant and Allen and Shariff Corporation is the PMC. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| 2013 |
Completion | Project expected to be completed
|
|
| Latest Events |
In April 2012, the main construction contract was awarded to Ed Zublin and construction started. In 2013, the project is expected to be completed. |
| Previous Events |
On 26 January 2012, the bids for the main construction contract were submitted (delayed for the second time from October 2011). In August 2011, the ITB for the main construction contract was issued. In July 2011, enabling works were completed. In June 2011, the RFQ for the construction contract was issued. In May 2011, a re-tendering process for the main construction contract was launched, the EOI (Expression of Interest) were submitted. In April 2011, the tender for the main construction contract was canceled. In September 2010, the bids for the main construction contract were submitted and the JV of Al Shafar Contracting CompanyAl Shafar Contracting Company , National Projects Construction (NPC) and Shimizu Corporation was the front runner. In Q2 2010, the ITB for the main construction contract was re-issued. In February 2010, the tender for the main construction contract was canceled. In December 2009, the enabling works contract was awarded to StrabagStrabag . In October 2009, companies were invited to prequalify for the main construction contract. In 2009, project announced. |
| Scope of Work |
Construction of a 358,000 sq. m. hospital including: - 688 beds - Parking for 1,500 car |
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2009 |
Announcement | Project announced
|
| Oct 2009 |
Construction | Companies invited to prequalify for main construction contract
|
| Dec 2009 |
Construction | Enabling works contract awarded to StrabagStrabag
|
| Feb 2010 |
Construction | Tender for the main construction contract canceled
|
| Q2 2010 |
Construction | ITB ofr main construction contract was re-issued
|
| Sep 2010 |
Construction | Bids for the construction contract submitted
- Brookfield Multiplex
- Ed Zueblin
- Jv of Al Shafar General Contracting Company, Shimizu Corporation and National Projects and Construction
- Saudi Binladin Group
|
|
| Apr 2011 |
Construction | Tender for the main construction contract canceled
|
| May 2011 |
Construction | Re-tendering for the main construction contract launched | | | Construction | EOI submitted
|
| Jun 2011 |
Construction | RFQ for construction contract issued
|
| Jul 2011 |
Construction | Enabling works completed
|
| Aug 2011 |
Construction | ITB for the main construction contract issued
|
| 26 Jan 2012 |
Construction | Bids for construction contract submitted
|
| Apr 2012 |
Construction | Construction contract awarded to Ed Zublin | | | Construction | Construction started
|
| 2013 |
Completion | Project expected to be completed
|
|
|
|
 |