| Also Known As |
: |
Heart of Doha |
| Country |
: |
Qatar |
| Project Value |
: |
N/A |
| Sector |
: |
Real Estate | Mixed Development |
|
Consultants |
: |
Allies and Morrison Architects
(Master Plan) |
Burns & McDonnell Engineering
(Design) |
Adjaye Associates
(Architect) |
|
PMC |
: |
Turner International Middle East
|
|
Contractors |
: |
BAUER International
(Enabling and Piling - Phase 1) |
Drake and Scull International
(MEP) |
| Profile Type |
: |
Standalone Project
|
| Associated Projects |
: |
| Related Projects (7) |
|
Phase: Construction - Execution
|
|
Completion: Q3 2014
|
|
|
|
| Background |
Msheireb PropertiesMsheireb Properties plans to build phase 1 of Msheireb in Doha, in Qatar. The project is part of Msheireb, a 350,000 sq.m. community development and will be developed into three sub-phases; a,b and c. Phase 1-a will include the construction of the Diwan Amiri Quarter including the Diwan Annex, Amiri Guard and the National Archive, a Heritage Quarter that includes the Eid Prayer Ground and 4 heritage houses, and infrastructure works. Phase 1-b will cover the construction of 15 buildings (Mandarin Oriental Hotel of 158 rooms and 91 apartments; 2 office buildings of 52 retail units; and 12 residential buildings with 180 apartments), a multi-purpose cultural forum, a shopping street, townhouses, a school and a mosque. Details of Phase 1-c were not revealed. Turner ConstructionTurner Construction is the PMC, Burns & McDonnell are the project design consultants, Adjaye Associates, Allies & Morrison Architects (master plan), Mossessian & Partners (schematic design), and John McAslan & Partners are the architects. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q4 2012 |
Completion | Phase 1-a expected to be completed | | 2013 | Completion | Phase 1-c expected to be completed | | Q3 2014 | Completion | Project including phase 1-b expected to be completed
|
|
| Latest Events |
In March 2012, the construction of 1-a was still ongoing, and the construction work of 1-b started. In Q4 2012, phase 1-a is expected to be completed. In 2013, phase 1-c is expected to be completed. In Q3 2014, the project including phase 1-b is expected to be completed. |
| Previous Events |
In early January 2012, the enabling and piling works of phases 1-b and 1-c were completed by BAUER International. In December 2011, the construction contract of 1-b was awarded to the Jv of Al Futtaim Carillion and Qatar Building Company. In July 2011, the construction of phase 1-a was ongoing. In February 2011, the ITB for the construction contract for phase 1-b was issued. In July 2010, the MEP contract was awarded to Drake and Scull InternationalDrake and Scull International . In April 2010, the main construction contract for phase 1-a was awarded to the JV of Hyundai Engineering & Construction CompanyHyundai Engineering & Construction Company and HBK Contracting CompanyHBK Contracting Company . In January 2010, the construction of phase 1-a started. In March 2010, the infrastructure work for phase 1-a was awarded to C.A.T. InternationalC.A.T. International . In 2010, the enabling works were completed. In Q2 2009, the enabling and piling contract for was awarded to Bauer International Qatar. In May 2009, the project was launched. |
| Scope of Work |
Construction of a mixed development including: Phase 1-a will include the construction of the Diwan Amiri Quarter including the Diwan Annex, Amiri Guard and the National Archive, a Heritage Quarter that includes the Eid Prayer Ground and 4 heritage houses, and infrastructure works. Phase 1-b will cover the construction of a multi-purpose cultural forum, offices, a shopping street, central luxury hotel and serviced apartments, townhouses, a school and a mosque. |
| Related Projects |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| May 2009 |
Announcement | Project launched
|
| Q2 2009 |
Construction | Enabling and piling contract for phase 1-a awarded to Bauer International Qatar
|
| Jan 2010 |
Construction | Construction of phase 1-a started
|
| 2010 |
Construction | Enabling woks completed
|
| Feb 2010 |
Construction | ITB for the construction contract for phase 1-b issued
|
| Mar 2010 |
Construction | Infrastructure work for phase 1-a awarded to C.A.T. InternationalC.A.T. International
|
| Apr 2010 |
Construction | Main contract for phase 1-a awarded to the JV of Hyundai Engineering & Construction CompanyHyundai Engineering & Construction Company and HBK Contracting CompanyHBK Contracting Company
|
| Jul 2010 |
Construction | MEP contract awarded to Drake and Scull InternationalDrake and Scull International
|
| Dec 2011 |
Construction | Contract of 1-b awarded to the Jv of Al Futtaim Carillion and Qatar Building Company
|
| Jan 2012 |
Construction | Enabling and piling works of phase 1-b and 1-c completed
|
| Mar 2012 |
Construction | Construction works of 1-b started
|
| Q4 2012 |
Completion | Phase 1-a expected to be completed
|
| 2013 |
Completion | Phase 1-c expected to be completed
|
| Q3 2014 |
Completion | Project including phase 1-b expected to be completed
|
|
|
|
 |