| Background |
The Kuwaiti Ministry of HealthMinistry of Health plans to expand its existing Al-Amiri Hospital in Safat, Kuwait City, Kuwait. The project will spread over 90,000 sq.m. and will comprise a 10-storey tower including a 4-storey podium, 360 beds, 65 clinics, a physiotherapy department, laboratories, a radiology department and a pharmacy. The project is part of the Health Ministry's plan to expand 9 existing hospitals in Kuwait. Hill-System Development Project Management is the PMC. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Apr 2012 |
DB | Contract expected to be awarded
|
| 2013 |
Completion | Project expected to be completed
|
|
| Latest Events |
In March 2012, the bids for the DB contract were under evaluation. In April 2012, the DB contract is expected to be awarded. In 2013, the project is expected to be completed. |
| Previous Events |
On 11 December 2011, the bids for the Design Build (DB) contract were submitted(delayed from 11 September 2011). In April 2011, the ITB for the DB contract was issued. In Q1 2011, the pre-qualification documents for the DB contract were submitted. In October 2010, the PMC contract was awarded to Hill-SDPM (the JV of Hill International and SDPM). |
| Scope of Work |
Construction of a 10-storey tower including: - 4-storey podium - 360 beds - 65 clinics - physiotherapy department - laboratories - radiology department - pharmacy |
|
| Schedule | Contract Phase/Phase | Description |
| Oct 2010 |
PMC | Contract awarded to Hill-SDPM
|
| Q1 2011 |
DB | Pre-qualification documents submitted
|
| Apr 2011 |
DB | ITB issued
|
| 11 Dec 2011 |
DB | Bids submitted
*Combined Group Contracting Company submitted the lowest bid
|
| Apr 2012 |
DB | Contract expected to be awarded
|
| 2013 |
Completion | Project expected to be completed
|
|
|