Kuwait MOH - Al-Amiri Hospital Expansion
Country : Kuwait
Project Value : N/A
Sector : Real Estate | Healthcare
PMC : Hill-System Development Project Management
Profile Type :  Standalone Project
Phase:
DB - Bid Evaluation
Completion: 2013
 
 
Owner : Ministry of Health - KuwaitMinistry of Health - KuwaitLoading... - Kuwait
Location :
Safat, Kuwait City , Al Assimah, Kuwait
Contract Type : DB - Design, Build
Facility Type : Hospital
Capacity : Built up area: 90,000 sq.m. 
360 beds
Main Usage :  Healthcare  
Background The Kuwaiti Ministry of HealthMinistry of HealthLoading... plans to expand its existing Al-Amiri Hospital in Safat, Kuwait City, Kuwait.

The project will spread over 90,000 sq.m. and will comprise a 10-storey tower including a 4-storey podium, 360 beds, 65 clinics, a physiotherapy department, laboratories, a radiology department and a pharmacy.

The project is part of the Health Ministry's plan to expand 9 existing hospitals in Kuwait.

Hill-System Development Project Management is the PMC.
Expected Events
Schedule Contract Phase/Phase Description
Apr 2012 DBContract expected to be awarded
2013 CompletionProject expected to be completed
Latest Events In March 2012, the bids for the DB contract were under evaluation.

In April 2012, the DB contract is expected to be awarded.

In 2013, the project is expected to be completed.
Previous Events On 11 December 2011, the bids for the Design Build (DB) contract were submitted(delayed from 11 September 2011).

In April 2011, the ITB for the DB contract was issued.

In Q1 2011, the pre-qualification documents for the DB contract were submitted.

In October 2010, the PMC contract was awarded to Hill-SDPM (the JV of Hill International and SDPM).
Scope of Work Construction of a 10-storey tower including:
- 4-storey podium
- 360 beds
- 65 clinics
- physiotherapy department
- laboratories
- radiology department
- pharmacy

Project Schedule

ScheduleContract Phase/PhaseDescription
Oct 2010 PMCContract awarded to Hill-SDPM
Q1 2011 DBPre-qualification documents submitted
Apr 2011 DBITB issued
11 Dec 2011 DBBids submitted
 
Prequalified Bidders
*Combined Group Contracting Company submitted the lowest bid
Apr 2012 DBContract expected to be awarded
2013 CompletionProject expected to be completed
 
Ministry of Health Building, Jamal Abdulnasser Street, Al Solaibeykhat Area, P.O. Box 5, Kuwait City Safat 13001, Kuwait, Al Assimah
Tel: +965 2487-7422 | Fax: +965 2486-5414 | Email: health@moh.gov.kw | Website: http://www.moh.gov.kw
 
Hill-System Development Project Management
PMC 
Al Jazeera Building, 1st and 2ndth floor, Al-Mutanabi Street, Kaifan, P.O. Box 13385, Kuwait Tel: +965 247-2574 | Fax: +965 247-2583 | Website: www.hill-sdpm.com
Print
 
  • SEARCH MIDDLE EAST PROJECTS
 
 
 
 
Panel