| Background |
The Supreme Committee For Town Planning of Oman plans to construct a 240 km, 4-lane carriageway along the Batinah coast in Oman. The purpose of the project is to ease traffic congestion and contribute to the economical growth and infrastructural development along the Batinah coast. The project will be carried out in phases; phase 1 is around 120 km long and phase 2 is 120 km long. National Engineering Services Pakistan and Partners (NESPAK) is the detailed design and engineering consultant. Consolidated Consultants Engineering and Environment is the PMC. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| H2 2012 |
Completion | Phase 1 expected to be completed | | 2014 | Completion | Project expected to be completed
|
|
| Latest Events |
In May 2012, the design of phase 2 and construction of phase 1 were ongoing. In H2 2012, phase 1 is expected to be completed. In 2014, the project is expected to be completed. |
| Previous Events |
In May 2011, the design of phase 2 was ongoing and construction of phase 1 was in progress. In May 2010, construction of phase 1 started. In February 2010, Consolidated Consultants Engineering and Environment was in negotiations with the Supreme Committee For Town Planning regarding the progress of the project. In Q4 2009, the PMC contract was awarded to Consolidated Consultants Engineering and Environment. In September 2009, the construction contract for section 1 of phase 1 was awarded to Makyol and the construction contract for section 2 of phase 1 was awarded to Nagarjuna Construction Company (NCC). On 18 August 2008, bidders submitted their proposals for the PMC contract. On 5 November 2008, the ITB for the construction contract of phase 1 was issued. On 26 January 2008, the ITB for the PMC contract was issued. In March 2006, the design consultancy contract was awarded to National Engineering Services Pakistan and Partners (NESPAK). In November 2005, bidders submitted their proposals for the design consultancy contract. In October 2005, the ITB for the design consultancy contract was issued. |
| Scope of Work |
Construction of a 240 km, 4-lane carriageway (intersected by a number of roundabouts and junctions): Phase 1 - Section 1 (60 km): stretching from Naseem roundabout to Sayyid Said bin Sultan Naval Base at Wudam al Sahel in the Wilayat of Musannah - Section 2 (60 km): stretching from Majees roundabout in Sohar to Khatmat Malaha in Wilayat Shinas Phase 2 (120 km) |
| Contract Packages |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| Oct 2005 |
Design | ITB issued
|
| Nov 2005 |
Design | Bidders submitted their proposals
|
| Mar 2006 |
Design | Contract awarded to National Engineering Services Pakistan and Partners
|
| 26 Jan 2008 |
PMC | ITB issued
|
| 18 Aug 2008 |
PMC | Bidders submitted their proposals
|
| 05 Nov 2008 |
Construction | ITB for phase 1's contract issued
|
| 06 Apr 2009 |
Construction | Bidders submitted their proposals for phase 1's contract
|
| Sep 2009 |
Construction | Contract for section 1 of phase 1 awarded to Makyol | | | Construction | Contract for section 2 of phase 1 was awarded to Nagarjuna Construction Company (NCC)
|
| Q4 2009 |
PMC | Contract awarded to Consolidated Consultants Engineering and Environment
- COWI and Partners
- Consolidated Consultants Engineering and Environment
- Dar Al Handasah Shair and PartnersDar Al Handasah Shair and Partners

- Driver Consult Oman
- JV of Konsult and Moderm Engineering Consultancy
- Mahab Ghodss Consulting Engineering
- Mashhoor Al Asfoor Engineering Consultancy
- Parsons International Limited
- Tecnic Consulting Engineers
|
- COWI and Partners
- Consolidated Consultants Engineering and Environment
- JV of Konsult and Moderm Engineering Consultancy
- Tecnic Consulting Engineers
|
- Consolidated Consultants Engineering and Environment
|
|
| H2 2010 |
Construction | Construction of phase 1 started
|
| H2 2012 |
Completion | Phase 1 expected to be completed
|
| 2014 |
Completion | Project expected to be completed
|
|
|