| Background |
Petroleum Development OmanPetroleum Development Oman (PDOPDO ) plans to build a gas processing plant next to Zauliyah oil field in Al Wusta, Oman. The project aims at processing the gas being produced in Zauliyah oil field. WorleyParsons EngineeringWorleyParsons Engineering is the FEED study consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| 03 Apr 2012 |
EPC | Bids submission deadline | | Q2 2012 | EPC | Contract expected to be awarded
|
| Q2 2014 |
Completion | Project expected to be completed
|
|
| Latest Events |
In February 2012, the FEED study was ongoing. 3 April 2012 is the bids submission deadline for the EPC contract. In Q2 2012, the EPC contract is expected to be awarded. In Q2 2014, the project is expected to be completed. |
| Previous Events |
On 1 October 2011, the ITB for the EPC contract was issued and the FEED study was ongoing. In H1 2011, work on the FEED study started (as part of the USD 300 million 5-year services contract signed between PDOPDO and WorleyParsons EngineeringWorleyParsons Engineering in 2009). |
| Scope of Work |
Construction of a gas processing plant including: - 7 well pads - Inlet separator - Gas conditioning unit - Export compressor - Trim cooler - Condensate/Glycol separator - Condensate stabilization unit - Off-spec condensate storage tank - Condensate export pumps - Water day tank - Water transfer pumps - Custody metering skid for export gas & stabilized condensate - AP Flare / closed drain system - LP Flare system - Nitrogen generation system - Instrument air system and fuel gas system - 12inch, 35 Km export gas pipeline to SOGL |
|
| Schedule | Contract Phase/Phase | Description |
| H1 2011 |
FEED | Study started
|
| Oct 2011 |
EPC | ITB issued
|
| 03 Apr 2012 |
EPC | Bids submission deadline
|
| Q2 2012 |
EPC | Contract expected to be awarded
|
| Q2 2014 |
Completion | Project expected to be completed
|
|
|