| Owner |
: |
Al Habtoor GroupAl Habtoor Group - UAE
|
| Location |
: |
Sheikh Zayed Road, Dubai, UAE
|
| Contract Type |
: |
Construction |
| Facility Type |
: |
Hotel Complex |
| Capacity |
: |
Land area: 92,900 sq.m. 1,675 rooms 3 hotels |
| Main Usage |
: |
Hotel |
|
| Background |
Al Habtoor GroupAl Habtoor Group plans to build a new hotel complex, Al Habtoor Palace Complex on Sheikh Zayed Road, Dubai, UAE. The project will replace the Metropolitan Hotel on a 92,900 sq.m. land area and will consist of 3 hotels of 1,675 rooms and two towers including a 1,000-seat theater. John R. Harris and PartnersJohn R. Harris and Partners is the concept design consultant and Khatib and Alami Consolidated Engineering CompanyKhatib and Alami Consolidated Engineering Company is the detailed design consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q3 2012 |
Design | Detailed design expected to be completed
|
| Q3 2012 |
Construction | ITB for the main construction contract expected to be issued | | Q3 2012 | Construction | Demolition of the Metropolitan Hotel expected to start | | Q4 2012 | Construction | Construction expected to start
|
| 2017 |
Completion | Project expected to be completed
|
|
| Latest Events |
In May 2012, the design of the complex was ongoing. In Q3 2012, the detailed design is expected to be completed, the ITB for the main construction contract is expected to be issued and the demolition of Metropolitan Hotel is expected to start. In Q4 2012, the construction is expected to start. In 2017, the project is expected to be completed. |
| Previous Events |
In 2011, the design of the complex started. |
| Scope of Work |
Construction of a 92,900 sq.m. hotel complex including: - 3 hotels of 1675 rooms - two towers - a 1,000-seat theater |
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2011 |
Design | Design started
|
| Q3 2012 |
Design | Detailed design expected to be completed | | | Construction | ITB for the main construction contract expected to be issued | | | Construction | Demolition of the Metropolitan Hotel expected to start
|
| Q4 2012 |
Construction | Construction expected to start
|
| 2017 |
Completion | Project expected to be completed
|
|
|