Covering major construction projects in the Middle East
|
|
 |
|
| Country |
: |
UAE |
| Project Value |
: |
USD 4,900,000,000 Estimated |
| Sector |
: |
Real Estate | Mixed Development |
|
Consultants |
: |
EWAN Architectural and Engineering Consultancy
(Masterplan) |
Hyder Consulting Middle East Limited
(Infrastructure) |
|
Contractor |
: |
National Projects and Construction
(Infrastructure) |
| Profile Type |
: |
Standalone Project
|
|
Phase: Construction - Execution
|
|
Completion: 2015
|
|
|
|
| Owner |
: |
Reem DevelopersReem Developers - UAE
|
| Location |
: |
Abu Dhabi, UAE
|
| Contract Type |
: |
Construction |
| Facility Type |
: |
Mixed Use Development |
| Capacity |
: |
Land area: 280,000 sq.m. |
|
| Background |
Reem DevelopersReem Developers plans to build Rawdhat Abu Dhabi, a mixed use development near the old Abu Dhabi airport. The project is the first "develop to lease" community in the UAE. It includes residential, commercial, leisure and entertainment facilities. The project will spread over an area of 280,000 sq. m. and will comprises of 76 plots divided to 3 residence types: Mediterranean, Modern and traditional. Reem DevelopersReem Developers will develop 6 out of the 76 plots while the rest is developed by private investors. The project will be built in two phases. Phase 1 includes 17 commercial developments and 44 residential developments. Phase 2 comprises of commercial developments. Ewan Architectural and Engineering Consultancy are the master plan consultant and Hyder ConsultingHyder Consulting is the infrastructure consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| 2015 |
Completion | Project expected to be completed
|
|
| Latest Events |
In January 2012, the construction of the project was ongoing and the owners refused to reveal who are the contractors. In 2015, the project is expected to be completed. |
| Previous Events |
In April 2010, the infrastructure work was completed. In December 2009, 80% of the infrastructure works was completed . In July 2008, the infrastructure contract was awarded to National Projects and Construction (NPC). In 2007, the master plan was completed by Ewan Architectural and Engineering Consultancy. In 2006, the project was launched. |
| Scope of Work |
Construction of a 280,000 sq. m. mixed use development including: - Low and mid-rise residential towers - Shopping malls - A courtyard - Parks - Schools - A mosque - Sports and play areas - Hospitals - A community center |
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2006 |
Announcement | Project launched
|
| 2007 |
Design | Masterplan completed by Ewan Architectural and Engineering Consultancy
|
| Jul 2008 |
Construction | Infrastructure contract awarded to National Projects and Construction
|
| Apr 2010 |
Construction | Infrastructure work completed
|
| 2015 |
Completion | Project expected to be completed
|
|
|
|
 |