| Country |
: |
Saudi Arabia |
| Project Value |
: |
USD 3,000,000,000 |
| Sector |
: |
Real Estate | Education |
|
Consultants |
: |
Saudi Consolidated Engineering Company (Khatib and Alami)
(Design ) |
Scado
( Engineering and design ) |
Hellmuth Obata and Kassabaum Incorporated - UAE
(Design ) |
Zuhair Fayez Partnership
(Design) |
Turner International Middle East
(Engineering and design ) |
|
PMC |
: |
Saudi Arabian Oil Company
|
|
Contractors |
: |
Saudi Binladin Group
(Construction and MEP - Residential and Civic) |
Saudi Oger Limited
(Construction and MEP - Research Park) |
| Profile Type |
: |
Master Project
|
| Associated Projects |
: |
Contract (2) |
|
| Completed
|
|
Completion: Dec 2011
|
|
|
|
| Owner |
: |
King Abdullah University of Science and Technology
|
| Developer |
: |
Emaar PropertiesEmaar Properties - UAE
|
| Location |
: |
Thuwal, Makkah , Saudi Arabia
|
| Contract Type |
: |
Construction |
| Facility Type |
: |
University |
| Capacity |
: |
Build up area: 36 million sq.m. 20,000 residents |
| Main Usage |
: |
Education |
|
| Background |
Saudi AramcoSaudi Aramco plans to develop King Abdullah University for Science and Technology (KAUST), a research university located in the coastal region of Thuwal, north of Jeddah. The project will cover an area of 36 million sq.m. and will include 64 residential buildings, villas, 21 research buildings, a marine and ocean research center (morc), a yacht club, a library, a theater, a mosque, a fire station, a clinic, a gas station, a supermarket, a golf club, a racket club, community schools, office buildings and other facilities. KAUST is divided to 4 main packages: Residential buildings, Civic buildings, a University Campus and a Marina. The University Campus is solely developed by Saudi AramcoSaudi Aramco whereas the rest is developed by Saudi AramcoSaudi Aramco and EmaarEmaar . Upon completion, the university will accommodate 20,000 residents. Zuhair Fayez Partners, HOK International, Khatib and Alami, Scado and Turner Construction Interntional are the engineering and design consultants and Saudi AramcoSaudi Aramco is the PMC. |
| Latest Events |
In the end of December 2011, the project was completed (delayed for the third time from Q1 2011). |
| Previous Events |
In Q3 2010, Residential package was completed (delayed from March 2009). In June 2009, university campus was completed. In November 2008, superstructures for all buildings were completed. In Q3 2008, substructures for all buildings were completed In April 2008, construction contract covering wood works, doors, gypsum works, and false ceilings was awarded to Saudi Company for Development of Construction and Trading Company (Sacodeco) . In March 2008, contract for the installation of aluminum glass facades was awarded to United Arab Aluminum Company. In February 2008, soil improvement was completed. In July 2007, substructure and superstructure IFC documents were issued. Construction contract for the research park was awarded to Saudi OgerSaudi Oger . Construction contract of the Residential and Civic buildings was awarded to Saudi BinladinSaudi Binladin . Contract for the Marina and water activities was awarded to HutaHuta . In 2005, the project was announced. |
| Scope of Work |
Construction of: - 64 residential buildings - 7 civic buildings (yacht club, galleria, bank, library, theater, good transfer station, waste transfer station) - villas - 21 research buildings - an ocean research center (morc) - Mosque - Fire station - Clinic - Gas station - Supermarket - Golf club, and racket club - Community schools - Office buildings and other facilities. |
| Financing Source |
Gulf International Bank (GIB), Arab Bank, Calyon Credit Agricole CIB and Emirates Bank International signed an USD 853 million agreement with Saudi OgerSaudi Oger to finance the residential part of KAUST project. |
| Contract Packages |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2005 |
Planning | Project announced
|
| Jul 2007 |
Construction | Contract for the Residential and Civic buildings awarded to Saudi BinladinSaudi Binladin | | | Construction | Contract for the Marina and water activities awarded to HutaHuta | | | Construction | Contract for the Research Park awarded to Saudi OgerSaudi Oger
|
| Mar 2008 |
Construction | Contract for the external facades awarded to United Arab Aluminium Company
|
| Apr 2008 |
Construction | Contract to cover wood works and minor construction awarded to Sacodeco
|
| Q3 2008 |
Construction | Substructure for all buildings completed
|
| Nov 2008 |
Construction | Superstructure for all buildings completed
|
| Jun 2009 |
Completion | University campus completed
|
| Q3 2010 |
Completion | Residential area completed
|
| Dec 2011 |
Completion | Project completed
|
|
|
Key:
Master Project
Package Project
Contract Project
|
|
 |