| Owner |
: |
DAMAC PropertiesDAMAC Properties - UAE
|
| Location |
: |
Al Sheikh Zayed City, 6th of October, Egypt
|
| Contract Type |
: |
Construction |
| Facility Type |
: |
Mixed Development |
| Capacity |
: |
723 retail units 454 office spaces |
|
| Background |
Damac PropertiesDamac Properties plans to develop Park Avenue , a mixed use development in Sheikh Zayed City in New Cairo. The project consists 723 retail units, 454 office spaces, and a parking with a capacity for 3,000 cars. The project will be implemented in 2 phases. Phase 1 will cover an area of 29,206 sq.m. and construction of 309 retail units and phase 2 will include the other parts of the project. ACE Consulting Engineers are the engineering consultants. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| 2013 |
Completion | Project expected to be completed
|
|
| Latest Events |
In April 2012, the construction of phase 2 was ongoing. In 2013, the project is expected to be completed. |
| Previous Events |
In February 2012, phase 1 was completed (delayed from December 2011). In Q4 2011, the construction of phase 2 started. In Q4 2010, construction of the project started and excavation works were completed. In September 2010, the main construction contract (including MEP works) was awarded to Industrial Construction and Engineering Company (SIAC). In Q4 2009, excavation works started by Al Dar Trading and Contracting Company. In November 2009, the excavation contract was awarded to Al Dar for Trading and Construction Company (DETAC). In October 2007, the project was launched. |
| Scope of Work |
Construction of a mixed development including: - 723 retail units - 454 office spaces - parking with capacity for 3,000 cars |
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| Nov 2009 |
Construction | Excavation work contract awarded to Dar for Trading and Construction Company (DETAC)
|
| Q4 2009 |
Construction | Excavation works started
|
| Sep 2010 |
Construction | Construction contract (including MEP works) awarded to Industrial construction and engineering company (SIAC)
|
| Q4 2010 |
Construction | Excavation works completed
|
| Q4 2011 |
Construction | Construction of phase 2 started
|
| Feb 2012 |
Construction | Phase 1 completed
|
| 2013 |
Completion | Project expected to be completed
|
|
|