| Owner |
: |
Manazel Real EstateManazel Real Estate - UAE
|
| Location |
: |
Al Raha Beach, Abu Dhabi, UAE
|
| Contract Type |
: |
DB - Design, Build |
| Facility Type |
: |
Mixed Development |
| Capacity |
: |
Land area: 130,639 sq.m. 1818 apartments 46 buildings |
|
| Background |
ManazelManazel plans to build Al Reef Development, a mixed development near Al Raha Beach, Abu Dhabi. The project will spread over an area of a 1 million sq. m and will include 1,700 apartments, schools, mosques, leisure, sports and entertainment facilities. It comprises of 46 apartment buildings, swimming pools, gymnasiums, children play areas and parking facilities. Crown Engineering Consultancy is the design consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Jul 2012 |
Construction | 343 residential units expected to be completed | | Sep 2012 | Construction | 340 residential units expected to be completed
|
| Dec 2012 |
Completion | Project expected to be completed
|
|
| Latest Events |
In April 2012, the construction of the project was ongoing and 347 residential units were completed. In July 2012, 343 residential units are expected to be completed. In September 2012, 340 residential units are expected to be completed. In December 2012, the project (452 residential units, retail store & community plaza) is expected to be completed (delayed for the second time from December 2010). |
| Previous Events |
In December 2011, 9 buildings and 336 residential units were completed. In September 2009, 35% of the construction was completed. In Q2 2008, piling and excavation works were completed by Fibrex CompanyFibrex Company . In 2007, DB contract contract was awarded to Fibrex CompanyFibrex Company . |
| Scope of Work |
Construction of a 1 million sq. m. mixed use development including: - 46 buildings (1,700 apartments) over an area of 130,000 sq. m. - Swimming pools - Gymnasiums - Children play areas - Parking facilities |
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2007 |
Announcement | Project announced | | | DB | Contract awarded to Fibrex CompanyFibrex Company
|
| Q2 2008 |
Construction | Piling and excavation works completed
|
| Sep 2009 |
Construction | 35% of construction completed
|
| Dec 2011 |
Construction | 9 buildings and 336 residential units completed
|
| Apr 2012 |
Construction | 347 residential units completed
|
| Jul 2012 |
Construction | 343 residential units expected to be completed
|
| Sep 2012 |
Construction | 340 residential units expected to be completed
|
| Dec 2012 |
Completion | Project expected to be completed
|
|
|