| Background |
The Iraqi Ministry of Electricity (MOE)Ministry of Electricity (MOE) plans to build a power plant in Al Najibiya, Al Basra, Iraq. The purpose of the project is to meet the increasing electricity demand in the country. The plant will use natural gas as feedstock. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Jun 2012 |
EPC | Mobilization expected to start | | Aug 2012 | EPC | Mobilization work expected to be completed | | Aug 2012 | EPC | Construction expected to start
|
| Q4 2013 |
Completion | Project expected to be completed
|
|
| Latest Events |
In June 2012, the mobilization works are expected to start. In August 2012, the mobilization works are expected to be completed and construction of the the plant is expected to start. In Q4 2013, the project is expected to be completed. |
| Previous Events |
In January 2012, the EPC contract was awarded to Enka Teknik. |
| Scope of Work |
Construction of a 500 MW gas fired power plant. |
|
| Schedule | Contract Phase/Phase | Description |
| Jan 2012 |
EPC | Contract awarded to Enka Teknik
|
| Jun 2012 |
EPC | Mobilization expected to start
|
| Aug 2012 |
EPC | Mobilization work expected to be completed | | | EPC | Construction expected to start
|
| Q4 2013 |
Completion | Project expected to be completed
|
|