Saudi Electricity Company (SEC)Saudi Electricity Company (SEC) plans to build PP12 in Riyadh, Saudi Arabia. The purpose of the project is to increase the power capacity in the region. The plant will be gas fired with a capacity of 2,175 MW. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Jun 2012 |
EPC | Construction expected to start
|
| 2015 |
Completion | Project expected to be completed
|
|
| Latest Events |
In May 2012, the EPC contract was awarded to Arabian Bemco Contracting Company LimitedArabian Bemco Contracting Company Limited . In June 2012, the construction of the project is expected to start. In 2015, the project is expected to be completed. |
| Previous Events |
On 4 September 2011, the bids for the EPC contract were submitted (bids submission deadline delayed from 4 July 2011). In Q2 2011, the ITB for the EPC contract was issued. In January 2011, the project was announced. |
| Scope of Work |
Construction of a 2,175 MW gas-fired power plant. |
|
|
|
|