| Also Known As |
: |
Blue City |
| Country |
: |
Oman |
| Project Value |
: |
USD 2,200,000,000 |
| Sector |
: |
Real Estate | Community Development |
|
Consultants |
: |
Thomson Perret and Lobb
(Design - Golf course) |
Foster and Partners
(Master Plan) |
|
PMC |
: |
Bovis Lend Lease
|
|
Contractor |
: |
AECO Development
(Design Build - phase 1) |
| Profile Type |
: |
Contract Project
|
| Associated Projects |
: |
| Related Projects (1) |
|
| On Hold
|
Last Activity: Construction - Execution
|
|
Initial Completion: 2012
|
|
|
|
| Background |
Al Sawadi Investment and Tourism CompanyAl Sawadi Investment and Tourism Company plans to build phase 1 of Al Madina A'Zarqa (Blue City), a community development in Oman. Phase 1 includes the construction of 200 villas, 2000 apartments, 4 resort hotels, 5 retail areas and 2 golf courses. Foster and Partner is the master planner. Bovis Lend Lease is the PMC. Thomson Perrett and Lobb is the golf course design consultant. |
| Latest Events |
In October 2011, the project was still on hold and no expected date to resume work was yet revealed. In 2012, the project was expected to be completed. |
| Previous Events |
In Q1 2011, the project was put on hold due to financial issues. In June 2010, 10% of the construction was completed. In Q1 2009, infrastructure and earth works were completed. In December 2008, construction of the housing village was completed. In April 2008, construction of 85% of the site facilities was completed. In Q1 2008, vertical construction started. In December 2007, groundwork started. In January 2006, DB contract for phase 1 was awarded to AECO Development (the JV of Aktor from Greece and Enka from Turkey) . |
| Scope of Work |
Construction of 200 villas, 5000 apartments, 5 retail areas, 2 golf courses, infrastructure and landscaping. |
| Contract Packages |
|
| Related Projects |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2005 |
Announcement | Project launched
|
| Jan 2006 |
Construction | DB contract awarded to AECO Development
|
| Dec 2007 |
Construction | Ground work started
|
| Q1 2008 |
Construction | Vertical construction started
|
| Dec 2008 |
Construction | Construction of the housing village completed
|
| Q1 2009 |
Construction | Infrastructure and earth works completed
|
| Q1 2011 |
Construction | Project put on hold
|
| 2012 |
Completion | Project was expected to be completed
|
|
|
Key:
Master Project
Package Project
Contract Project
|
|
 |