| Owner |
: |
Jv of Qatar Petroleum and Qatar Shell GTL Limited
|
| Shareholders |
: |
Qatar PetroleumQatar Petroleum - Qatar
Qatar Shell GTL - Qatar
|
| Location |
: |
Doha, Qatar
|
| Facility Type |
: |
GTL and NGL plants |
| Capacity |
: |
140,000 bpd of GTL 120,000 bpd of NGL |
|
| Background |
The joint venture of Qatar PetroleumQatar Petroleum and Qatar Shell GTL plans to construct an integrated GTL complex in Ras Laffan Industrial City, Qatar. The Pearl GTL project includes the development of offshore natural gas resources in Qatar's North Field, transporting and processing the gas to extract natural gas liquids and ethane, and the conversion of the remaining gas into clean liquid hydrocarbon products through the construction of the integrated GTL complex in Ras Laffan Industrial City. The Pearl GTL complex will consist of two 70,000 bpd GTL trains and two 60,000 bpd NGL plants with their associated facilities. The plant will produce a range of clean liquid products and fuels, comprising naphtha, GTL fuel, normal paraffins, kerosene and lubricant base oils. The JV of MW Kellogg and JGC is the FEED study consultant. |
| Latest Events |
In July 2011, first production started, marking the completion of the project. |
| Previous Events |
In June 2011,commissioning of the plants was in progress. In January 2011, construction was near completion. QP and Qatar Shell GTL signed a frame agreement with Technip whereby Technip will assist in maintenance, commissioning and any future scope changes or expansion. In July 2008, Shell announced that 45%of the project was completed. In Q1 2007, construction of the plants started. In 2006, all major EPC contracts were awarded. In November 2005, FEED studies were completed. In July 2004, Qatar PetroleumQatar Petroleum and Qatar Shell GTL signed the Development and Production Sharing Agreement (DPSA). In March 2004, the FEED contract was awarded to the JV of MW Kellogg and JGC. |
| Scope of Work |
The project includes the construction of: - Two 70,000 bpd GTL trains - Two 60,000 bpd NGL plants - Captive power plant - Effluent treatment plant - Associated facilities |
| Financing Source |
Shell will provide 100% of project funding. |
| Contract Packages |
| Type |
Project Name |
Contract Value |
 |
QP/Qatar Shell GTL - PearL GTL - Onshore Package C6 - Captive Power Plant |
USD 980,000,000 |
 |
QP/Qatar Shell GTL- Pearl GTL - Offshore Package |
USD 1,200,000,000 |
 |
QP/Qatar Shell GTL- Pearl GTL - Onshore Package C2 |
USD 900,000,000 |
 |
QP/Qatar Shell GTL- Pearl GTL - Onshore Package C3 |
USD 400,000,000 |
 |
QP/Qatar Shell GTL- Pearl GTL - Onshore Package C4 |
USD 1,750,000,000 |
 |
QP/Qatar Shell GTL- Pearl GTL - Onshore Package C5 |
USD 1,480,000,000 |
 |
QP/Qatar Shell GTL- Pearl GTL - Onshore Package C8 - Effluent Treatment Plant |
- |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| Mar 2004 |
FEED | Contract awarded to JV of MW Kellogg and JGC
|
| Jul 2004 |
Planning | QP and Qatar Shell GTL Limited signed the Development and Production Sharing Agreement (DPSA).
|
| Nov 2005 |
FEED | Study completed
|
| 2006 |
EPC | Contracts awarded
|
| Q1 2007 |
EPC | Construction started
|
| Jul 2008 |
EPC | 45% of the project completed
|
| Jul 2011 |
Completion | Project completed
|
|
|