| Owner |
: |
SonatrachSonatrach - Algeria
|
| Location |
: |
Algeria
|
| Contract Type |
: |
EPC - Engineering, Procurement, Construction |
| Facility Type |
: |
Refinery |
| Capacity |
: |
300,000 bpd of oil |
|
| Background |
SonatrachSonatrach plans to construct an oil refinery in Tiaret (Hauts Plateaux mountains), in northwest Algeria. The Tiaret refinery aims at processing Saharan Blend crude oil. Output of the refinery will include gasoline, gasoil, jet fuel, butane, propane and naphtha. Jacobs Consultancy and HSBCHSBC are the feasibility study consultants. SonatrachSonatrach carried out the engineering development of the project. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| 2014 |
Completion | Project expected to be completed
|
|
| Latest Events |
In March 2011, the tendering and bidding process for the FEED contract was delayed for the fourth time from January 2010. In 2014, the project is expected to be completed (delayed from 2013). |
| Previous Events |
In March 2010, the project was put on hold due to the investigations of the SonatrachSonatrach corruption incident in January 2010. On 19 October 2009, technical bids for the FEED contract were opened. In 2009, the ITB for the FEED contract was issued. In April 2009, 15 companies submitted their request for pre-qualification (RFP) applications for the FEED contract. In February 2008, SonatrachSonatrach carried out the preliminary engineering development of the project. In Q3 2007, the feasibility study was finalized. In October 2007, SonatrachSonatrach reconsidered seeking an international partner. In mid 2006, SonatrachSonatrach dropped the bid evaluation and canceled the tendering. In 2006, SonatrachSonatrach was seeking an international partner to hold 35% in a joint venture in order to develop the refinery. SonatrachSonatrach was negotiating with CNPC and Total. In Q4 2005, the project was announced. |
| Scope of Work |
Construction of a 300,000 bpd oil refinery along with all its related facilities. |
|
| Schedule | Contract Phase/Phase | Description |
| Jun 2006 |
Study | Pre- feasibility study started
|
| Q3 2007 |
Study | Feasibility study finalised
|
| Apr 2009 |
FEED | Bidders submitted their pre-qualification applications
- JV of CB and I Lummus
- Jv of Chiyoda Corporation and Saipem SpA
- Sinopec International Petroleum
- Technip
|
|
| 19 Oct 2009 |
FEED | Technical bids were opened
|
| Mar 2010 |
FEED | Project put on hold
|
| 2014 |
Completion | Project expected to be completed
|
|
|