Sadara Chemical Company - Jubail Petrochemicals Complex
Country : Saudi Arabia
Project Value : USD 20,000,000,000 Estimated
Sector : Petrochemicals | Olefins & Aromatics
Consultant : KBR (FEED)
PMC : KBR
Profile Type :  Master Project
Associated Projects : Contract (14)  | Related Projects (1)
Phase:
EPC - Tendering & Bidding
Completion: 2015
 
 
Owner : Sadara Chemical CompanySadara Chemical CompanyLoading... - Saudi Arabia
Shareholders : Saudi Arabian Oil CompanySaudi Arabian Oil CompanyLoading... - Saudi Arabia
Dow Chemical CompanyDow Chemical CompanyLoading... - United States
Location :
Jubail Industrial City 2, Jubail, Al Sharqiyah , Saudi Arabia
Contract Type : EPC - Engineering, Procurement, Construction
Facility Type : Petrochemicals Complex
Capacity : 1.3 million t/y of ethylene 
400,000 t/y of propylene
Background Sadara Chemical CompanySadara Chemical CompanyLoading... plans to build a petrochemicals complex in Jubail.

The complex was initially planned to be built in Ras Tannura.

SatorpSatorpLoading... is the feedstock provider.

Dow Chemical CompanyDow Chemical CompanyLoading... is the technology licensing provider.

KBRKBRLoading... is the PMC and FEED study consultant.
Expected Events
Schedule Contract Phase/Phase Description
Q2 2012 EPCContracts for the Hydrogen, Carbon Monoxide and Ammonia Plants, PMD and TDI Production Facilities, tank farm and ethane cracker packages expected to be awarded
2015 CompletionProject expected to be completed
Latest Events In April 2012, a USD 380 million contract was signed between Sadara and Linde Group. Linde will provide ammonia (NH3), carbon monoxide (CO) and hydrogen (H2) to Sadara.

In Q2 2012, the EPC contracts for the Hydrogen, Carbon Monoxide and Ammonia Plants, PMD and TDI Production Facilities, tank farm and ethane cracker packages are expected to be awarded.

In H1 2012, construction is expected to begin.

In 2015, the project is expected to be completed.
Previous Events In March 2012, construction of the Aniline-Formalin and DNT-Nitric Facilities started and the engineering works of the Offsites and Utilities package started.

In January 2012, engineering works for the main tank farm package started.

In December 2011, the EPC contract for the main tank farm was awarded to Daewoo Engineering and ConstructionDaewoo Engineering and ConstructionLoading....

In November 2011, the EPC contract for the Aniline-Formalin and DNT-Nitric Facilities package was awarded to DaelimDaelimLoading....

In September 2011, the EPC and management contract for the Chlorine plant package was awarded to Jacobs EngineeringJacobs EngineeringLoading....

In July 2011, the joint venture partners formed the Sadara Chemical CompanySadara Chemical CompanyLoading... and the EPC contract for the Mixed Feed Cracker package was awarded to DaelimDaelimLoading... Saudi Arabia.

In Q2 2011, the FEED study was completed.

On August 3 2010, AramcoAramcoLoading... and DowDowLoading... announced their final decision to relocate the complex from Ras Tannura to Jubail Industrial City 2.

In Q4 2008, the FEED study contract for the aromatics, ethylene, utilities and the hydrocarbon packages was awarded to Foster WheelerFoster WheelerLoading... and the FEED contract for the chlorine plant was awarded to Jacobs EngineeringJacobs EngineeringLoading....

In July 2007, the PMC contract was awarded to KBRKBRLoading.... KBRKBRLoading... would carry out project management services, including the preparation of tender documents, evaluation of technical proposals and supervision of the execution phase. Also the FEED would be jointly managed by Saudi AramcoAramcoLoading... and Dow Chemical CompanyDow Chemical CompanyLoading... with KBRKBRLoading... responsible for its implementation.

In May 2007, Saudi AramcoAramcoLoading... and Dow Chemical CompanyDow Chemical CompanyLoading... signed the MoU for developing the refinery and petrochemicals complex.
Scope of Work Work includes the construction of:

- Ethane/naphtha steam cracker to produce 1.3 million t/y of ethylene and 400,000 t/y of propylene
- Aniline-Formalin and DNT-Nitric Facilities
- Chlorine plant
- Hydrogen, Carbon Monoxide and Ammonia Plants
- PMD and TDI Production Facilities
- Tank farm
- Offsites and utilities
Financing Source Royal Bank of ScotlandRoyal Bank of ScotlandLoading... is the financial adviser.

The project will be funded by 70% Debt, 30% Equity. The joint venture plans to float a 30% stake in an IPO and will make a decision on the size and timing of the IPO after completing early engineering.

In Q3 2012, Sadara is expected to complete the financing with a financial close expected in Q1 2013.

In Q2 2012, AramcoAramcoLoading... and DowDowLoading... are expected to start negotiations with commercial banks regarding the financing deals. Nine export credit agencies (ECAs), including the local Pubilc Investment Fund, are in advanced stages of negotiations to supply direct loans or loan insurances.

In September 2011, AramcoAramcoLoading... and DowDowLoading... started approaching export credit agencies (ECAs) for financing the project.
Contract Packages
Type Project Name Contract Value
Sadara Chemical Company - Jubail Petrochemicals Complex - Aniline-Formalin and DNT-Nitric Facilities -
Sadara Chemical Company - Jubail Petrochemicals Complex - Hydrogen, Carbon Monoxide and Ammonia Plants USD 450,000,000
Sadara Chemical Company - Jubail Petrochemicals Complex - Offsites and Utilities USD 1,800,000,000
Sadara Chemical Company - Jubail Petrochemicals Complex - Chlorine Plant -
Sadara Chemical Company - Jubail Petrochemicals Complex - Cycrogenic Tank Farm -
Sadara Chemical Company - Jubail Petrochemicals Complex - Ethylene Oxide Plant USD 600,000,000
Sadara Chemical Company - Jubail Petrochemicals Complex - Hydrogen Plant -
Sadara Chemical Company - Jubail Petrochemicals Complex - Main Tank Farm USD 400,000,000
Sadara Chemical Company - Jubail Petrochemicals Complex - Mixed Feed Cracker USD 2,000,000,000
Sadara Chemical Company - Jubail Petrochemicals Complex - Oxygen Plant -
Sadara Chemical Company - Jubail Petrochemicals Complex - PMD and TDI Production Facilities -
Sadara Chemical Company - Jubail Petrochemicals Complex - Propylene Oxide Unit -
Sadara Chemical Company - Jubail Petrochemicals Complex - Third Tank Farm -
Sahara Chemical Company - Petrochemicals Complex - Marine Package USD 100,000,000
Related Projects
Project News
28-Nov-2011 Dow & Saudi Aramco Announce Official Formation of Sadara, Board of Directors and Key Officers - Press Release
09-Oct-2011 Saudi Aramco, Dow Sign Sadara JV Shareholders' Agreement - Press Release
26-Jul-2011 Aramco, Dow in $20b venture - Gulf News
04-Aug-2010 Aramco-Dow joint venture petchem project progresses - The Saudi Gazette
18-Feb-2009 Aramco, Dow plan to drop troubled RBS - Gulf News
03-Jan-2009 Aramco, Dow seek cost cuts - The Saudi Gazette
12-Jul-2007 Saudi Aramco and Dow Chemical Select KBR as Project Management Contractor for the Proposed Ras Tanura Integrated Project - Press Release
12-May-2007 Saudi Aramco and Dow announce the signing of the MoU - Press Release
11-Jul-2006 Saudi Aramco Selects Dow Chemical Company for Negotiations on New Petrochem Complex - Saudi Press Agency
» More News

Project Schedule

ScheduleContract Phase/PhaseDescription
May 2007 PlanningMoU signed between AramcoAramcoLoading... and DowDowLoading... Chemical
 
Bidders Selected
Jul 2007 PMCContract awarded to KBRKBRLoading... for the whole complex
 
Prequalified Awarded
  • KBR
 FEEDContract awarded to KBRKBRLoading...
Q4 2008 FEEDContract awarded to Foster WheelerFoster WheelerLoading... for the aromatics, ethylene, utilities and the hydrocarbon packages
Q2 2011 FEEDStudy completed
Jul 2011 EPCMContract for the offsites and utilities package awarded To Fluor
 EPCContract for the Mixed Feed Cracker package awarded to DaelimDaelimLoading... Saudi Arabia
Sep 2011 EPCContract for the Chlorine plant package awarded to Jacobs EngineeringJacobs EngineeringLoading...
Nov 2011 EPCContract for the Aniline-Formalin and DNT-Nitric Facilities package awarded to DaelimDaelimLoading...
Dec 2011 EPCContract for the main tank farm awarded to Daewoo Engineering and ConstructionDaewoo Engineering and ConstructionLoading...
Q2 2012 EPCContracts for the Hydrogen, Carbon Monoxide and Ammonia Plants, PMD and TDI Production Facilities, tank farm and ethane cracker packages expected to be awarded
2015 CompletionProject expected to be completed

Project News

28-Nov-2011 Dow & Saudi Aramco Announce Official Formation of Sadara, Board of Directors and Key Officers - Press Release
09-Oct-2011 Saudi Aramco, Dow Sign Sadara JV Shareholders' Agreement - Press Release
26-Jul-2011 Aramco, Dow in $20b venture - Gulf News
04-Aug-2010 Aramco-Dow joint venture petchem project progresses - The Saudi Gazette
18-Feb-2009 Aramco, Dow plan to drop troubled RBS - Gulf News
03-Jan-2009 Aramco, Dow seek cost cuts - The Saudi Gazette
12-Jul-2007 Saudi Aramco and Dow Chemical Select KBR as Project Management Contractor for the Proposed Ras Tanura Integrated Project - Press Release
12-May-2007 Saudi Aramco and Dow announce the signing of the MoU - Press Release
11-Jul-2006 Saudi Aramco Selects Dow Chemical Company for Negotiations on New Petrochem Complex - Saudi Press Agency
 
Sadara Chemical Company
Owner 
C/O: Aramco, Saeed Tower, Dammam Khobar Highway, Al Sharqiyah, P.O. Box 151, Al Khobar, Saudi Arabia Tel: +966 3-872-0115 | Fax: +966 3-814-7063 | Email: webmaster@aramco.com.sa | Website: www.saudiaramco.com
  • Name: Saleh Subaie
    Position: Planning Supervisor
    Tel: +966 3-578-9773
 
KBR
Consultant - FEED
Al Sharqiyah, P.O. Box 3474, Al Khobar 31952, Saudi Arabia
Tel: +966 3-858-8877 | Fax: +966 3-873-0176 | Website: www.kbr.com
  • Name: Raed Ghanem
    Position: Senior Project Manager
    Tel: +966 3-891-3456 ext:1068
 
KBR
PMC 
Al Sharqiyah, P.O. Box 3474, Al Khobar 31952, Saudi Arabia
Tel: +966 3-858-8877 | Fax: +966 3-873-0176 | Website: www.kbr.com
  • Name: Raed Ghanem
    Position: Senior Project Manager
    Tel: +966 3-891-3456 ext:1068
 
Dow Chemical Company
Shareholder 
Al Attar Business Tower, 22nd Floor, Sheikh Zayed Road, P.O. Box 7893, Dubai, United Arab Emirates, Dubai
Tel: +971 4-332-8866 | Fax: +971 4-332-8280
 
Saeed Tower, Dammam Khobar Highway, P.O. Box 151, Al Khobar 31952, Saudi Arabia, Al Sharqiyah
Tel: +966 3-872-0115,+966 3-810-6999 | Fax: +966 3-814-7063,+966 3-873-8190 | Email: webmaster@aramco.com.sa | Website: www.saudiaramco.com
Key:    Master Project    Package Project    Contract Project
Print
 
  • SEARCH MIDDLE EAST PROJECTS
 
 
 
 
Panel