| Country |
: |
Qatar |
| Project Value |
: |
USD 1,360,000,000 Estimated |
| Sector |
: |
Real Estate | Residential |
|
Consultant |
: |
Aecom Arabia Company Limited
(Design) |
|
PMC |
: |
Qatar Project Management
|
|
Contractors |
: |
Bilfinger Berger
(Infrastructure and Construction - Phase 1 ) |
Shapoorji Pallonji
(DB - Amenities phase 1) |
|
Sub-Contractor |
: |
Voltas Limited
(MEP) |
| Profile Type |
: |
Standalone Project
|
|
Phase: Construction - Execution
|
|
Completion: Q1 2015
|
|
|
|
| Owner |
: |
Barwa Real Estate CompanyBarwa Real Estate Company - Qatar
|
| Location |
: |
Musaimeer, Doha, Qatar
|
| Contract Type |
: |
Construction |
| Facility Type |
: |
Residential development |
| Capacity |
: |
Total land area: 2.7 million sq.m. Total built up area: 97,000 sq.m. 8,000 housing units |
| Main Usage |
: |
Residential |
|
| Background |
Barwa Real Estate CompanyBarwa Real Estate Company plans to build Barwa City, a residential development located in Musaimeer, Doha. Barwa City will cover an area of 97,000 million sq. m. and will include a 40-storey 4-star hotel, 7 schools, a 200-bed hospital, mosques, parks, shopping complexes, health facilities and oter several facilities. The project will be implemented in 2 phases: phase 1 will include 128 buildings, 1024 studio units, 6,000 residential units, two K-12 school, health and fitness club, central park, multipurpose hall, commercial zone, and infrastructure works; and phase 2 will include 2,000 units, a 250 bed hospital, a bank, a school, a retail outlet, and a commercial complex. Barwa City will accommodate 25,000 people. AECOMAECOM is the design consultant for phase 1, Cansult Maunsell is the design consultant for phase 2 and Qatar Project Management CompanyQatar Project Management Company (QPM) is the PMC. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Jun 2012 |
Construction | The schedule for phase 2 expected to be revealed
|
| Q1 2015 |
Completion | Project expected to be completed
|
|
| Latest Events |
In June 2012, the schedule for phase 2 is expected to be revealed. In Q1 2015, the project is expected to be completed. |
| Previous Events |
In March 2012, phase 1 was completed (delayed from Q4 2011). In December 2010, the construction of the amenities started. In late September 2010, the design for the amenities was completed and excavation works started. In June 2010, a Design Build contract for amenities in phase 1 was awarded to Shapoorji Pallonji (worth USD 185.6 million) and 50% of the construction work in phase 1 was completed. In May 2007, the infrastructure and construction contract for phase 1 was awarded to Bilfinger Berger. |
| Scope of Work |
Construction of a 2.7 million sq.m. development including: Phase 1: Bilfinger Berger construction contract includes: - 128 buildings - 1024 studio units - 6,000 residential units - Infrastructure works include roads, landscaping, substations and pumping stations Shapoorji Pallonji contract includes: - two K-12 schools - health and fitness club - central park - multipurpose hall - commercial zone Phase 2: - 2,000 units - A 250 bed hospital - A bank - A school - A retail outlet - A commercial complex |
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| May 2007 |
Construction | Infrastructure and construction contract of phase 1 awarded to Bilfinger Berger
|
| Jun 2010 |
DB | Contract for amenities in phase 1 awarded to Shapoorji Pallonji | | | Construction | 50% of the construction works on phase 1completed
|
| Sep 2010 |
Design | Design of the amenities completed | | | Construction | Excavation works for the amenities started
|
| Dec 2010 |
Construction | Construction of the amenities started
|
| Mar 2012 |
Construction | Phase 1 completed
|
| Jun 2012 |
Construction | The schedule for phase 2 expected to be revealed
|
| Q1 2015 |
Completion | Project expected to be completed
|
|
|
|
 |