ENI/Oxy/KOGAS/Missan Oil Company - Zubair Oil Field Redevelopment
Country : Iraq
Project Value : USD 6,500,000,000
Sector : Oil and Gas | Exploration & Production
Contractors : Halliburton (Drilling) |  Baker Hughes (EPC) |  Iraqi Drilling Company (Drilling)
Profile Type :  Master Project
Associated Projects : Contract (2)
Phase:
Construction - Execution
Completion: 2016
 
 
Owner : Consortium of Missan Oil Company, KOGAS, ENI Group and Occidental Middle East Development Company
Shareholders : Missan Oil Company - Iraq - 25.00 %
Occidental Oil and Gas InternationalOccidental Oil and Gas InternationalLoading... - United States - 23.44 %
ENI GroupENI GroupLoading... - Italy - 32.81 %
KOGAS - Japan - 18.75 %
Location :
Zubair, Al Basra, Iraq
Contract Type : Construction
Facility Type : Oil field redevelopment
Capacity : 1.125 million bpd of oil
Background The consortium of ENIENILoading..., Occidental Petroleum, KOGASKOGASLoading... and Missan Oil Company (led by ENIENILoading...) plans to expand the Zubair Oil Field in Basra, Southern Iraq.

The project aims at increasing production from 182,000 bpd to 1.125 million bpd by 2016.
Expected Events
Schedule Contract Phase/Phase Description
2016 CompletionProject expected to be completed
Latest Events In January 2012, engineering works for the early production facilities and rehabilitation of production facilities packages were ongoing.

In 2016, the project is expected to be completed.
Previous Events In December 2011, the drilling contract was awarded to Baker HughesBaker HughesLoading....

In October 2011, bids for the drilling contract were under evaluation.

In May 2011, the Iraqi drilling Company started its drilling work on the project.

In January 2011, a USD 250 million contract to drill 23 new wells was awarded to the Iraqi Drilling Company. The deal also includes the overhauling of 63 old wells.

In August 2010, an energy services contract was awarded to Halliburton. The contract includes wire-line logging, perforating, acidising and well testing on 20 wells.

In November 2009, a technical services contract to redevelop the Zubair field was signed between SOCSOCLoading... and the consortium of ENIENILoading..., Occidental Petroleum CompanyOccidental Petroleum CompanyLoading..., KGOC and Missan Oil Company.
Scope of Work Expansion of the oil field including:

- Drilling of 60 wells
- Wire-line logging
- Perforating
- Acidifying and well testing
- Revamp of existing production facilities
- Early production facilities
Contract Packages
Type Project Name Contract Value
ENI/Oxy/KOGAS/Missan Oil Company - Zubair Oil Field Redevelopment - Early Production Facilities USD 800,000,000
ENI/Oxy/KOGAS/Missan Oil Company - Zubair Oil Field Redevelopment - Rehabilitation of Production Facilities -
Project News
16-May-2011 Iraqi drilling firm commences operation in Zubair oil field - The Daily Star

Project Schedule

ScheduleContract Phase/PhaseDescription
Nov 2009 BOOContract awarded to the consortium of ENIENILoading...,Occidental Petroleum, KOGASKOGASLoading... and Missan Oil Company
Aug 2010 ConstructionEnergy sevices contract awarded to Halliburton
Sep 2010 ConstructionDrilling work started
Jan 2011 ConstructionDrlling contract awarded to Iraqi drilling Company to drill 23 new wells
May 2011 ConstructionIraqi drilling Company started its drilling work
Dec 2011 ConstructionDrilling contract awarded to Baker HughesBaker HughesLoading...
2016 CompletionProject expected to be completed

Project News

16-May-2011 Iraqi drilling firm commences operation in Zubair oil field - The Daily Star
 
Consortium of Missan Oil Company, KOGAS, ENI Group and Occidental Middle East Development Company
Owner 
Missan Oil Company
AMARAH CITY - CENTER / AWWASHAH
Tel: +964 4-331-3472 | Fax: +964 4-331-3471 | Website: www.mociraq.com
  • Name: Sami Nagi
    Position: Head of Oilfield Operations
KOGAS
93 Dolmaro(215. Jeongja-dong), Bundang-gu, Seongnam, Gyeonggi-do, 463-754, Korea
Tel: +82 31-710-0114 | Fax: +82 31-710-0117 | Website: www.kogas.or.kr
  • Name: Hapshu Soh
    Position: Iraq Projects Manager
    Tel: +82 31-784-6563
ENI Group Building, Piazzale Enrico Mattei 1 Street, Rome 00144, 00144, Italy
Tel: +39 065-9821 | Fax: +39 06-5982-2141 | Email: segretriasoietaria.azionish@eni.com,info.governance@eni.com | Website: http://www.eni.it
  • Name: Claudio Descalzi
    Position: Chief Operating Officer, Exploration and Production
Occidental Towers, 4th Street, Muroor Area, P.O. Box 73243, Abu Dhabi, United Arab Emirates
Tel: +971 2-691-7200 | Fax: +971 2-645-0395
  • Name: John Newbery
    Position: Business Development Director
 
Halliburton
Contractor - Drilling
Al Sharqiyah, Al Khobar 31952, Saudi Arabia
Tel: +966 3-838-9999 | Fax: +966 3-838-9000 | Website: http://www.halliburton.com/
 
Iraqi Drilling Company
Contractor - Drilling
Al Nidhal Street, Park Al Saadoon, P.O. Box 19312, Iraq Tel: +964 1719-1773 | Fax: +964 1719-8278 | Email: idc@idc.gov.iq | Website: http://www.oil.gov.iq
 
Baker Hughes
Contractor - EPC
Sheikh Zayed Street, Techno Park, Dubai, UAE Tel: +971 4-811-4000 | Website: http://www.bakerhughes.com
Key:    Master Project    Package Project    Contract Project
Print
 
  • SEARCH MIDDLE EAST PROJECTS
 
 
 
 
Panel