| Country |
: |
Kuwait |
| Project Value |
: |
N/A |
| Sector |
: |
Power and Water | Sewage Treatment |
|
Consultants |
: |
Dar Al Handasah Shair and Partners
(Design) |
Fichtner Consulting Engineers
(Technical) |
| Profile Type |
: |
Contract Project
|
| Associated Projects |
: |
Contract (1) |
|
Phase: Developer DBO - Tendering & Bidding
|
|
Completion: 2015
|
|
|
|
| Background |
The Ministry of Public WorksMinistry of Public Works (MPW), through the Partnerships Technical Bureau (PTB), plans to build the Umm Al Haiman sewage treatment plant in Al Ahmadi, Kuwait. The purpose of the project is to meet the growing population's needs in the area. The project is phase 1 of the Umm Al Haiman Sewage Treatment Plant and will have a capacity of 500,000 cu.m./d. Phase 2 will have a capacity of 200,000 cu.m./d. Fichtner Consulting EngineersFichtner Consulting Engineers is the technical adviser. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Jun 2012 |
DBO | RFQ expected to be issued | | Q3 2012 | DBO | RFP expected to be issued
|
| 2015 |
Completion | Project expected to be completed
|
|
| Latest Events |
In June 2012, the RFQ for the DBO contract is expected to be issued. In Q3 2012, the RFP for the DBO contract is expected to be issued. In 2015, the project is expected to be completed. |
| Previous Events |
On 15 March 2012, companies submitted their EOIs. On 15 January 2012, the Ministry of Public WorksMinistry of Public Works invited companies to submit their EOI for the DBO contract. In December 2011, the technical and financial study was completed. In October 2011, the technical and financial study was ongoing. In April 2011, the transaction advisory services contract was awarded to Fichtner Consulting EngineersFichtner Consulting Engineers as technical adviser, HSBCHSBC as financial adviser and Norton RoseNorton Rose as legal adviser (delayed from March 2011) and the technical and financial study started. In March 2011, the bids for the transaction advisory services contract were still under evaluation. In February 2011, the design of the sewage treatment plant was completed. In January 2011, 9 bidders submitted their proposals for the transaction advisory services contract. The design was in progress. In Q4 2010, the RFP for the transaction advisory services contract was issued. In September 2010, bidders submitted their pre-qualification documents for the transaction advisory services contract. The awarded consultant will be responsible for the technical, financial, environmental, and legal aspects of the project. In August 2010, the RFQ for the transaction advisory services contract was issued. In January 2009, the design consultancy contract was awarded to Dar Al HandasahDar Al Handasah . In August 2007, bids for the design consultancy contract were submitted. In April 2007, the RFQ for the design consultancy contract was issued. |
| Scope of Work |
Construction of a 500,000 cu.m./d. sewage treatment plant. |
| Financing Source |
HSBCHSBC is the financial adviser. Norton RoseNorton Rose is the legal adviser. |
| Contract Packages |
|
|
| Schedule | Contract Phase/Phase | Description |
| Apr 2007 |
Design | RFQ issued
|
| Aug 2007 |
Design | Bidders submitted their proposals
|
| Jan 2009 |
Design | Design consultancy contract awarded to Dar Al HandasahDar Al Handasah
|
| Aug 2010 |
Consultant | RFQ for the transaction advisory services contract issued
|
| Sep 2010 |
Consultant | Bidders submitted their pre-qualification documents for the transaction advisory services contract
|
| Q4 2010 |
Consultant | RFP for the transaction advisory services contract issued
|
| Jan 2011 |
Consultant | 9 bidders submitted their proposals for the transaction advisory services contract
|
| Feb 2011 |
Design | Design completed
|
| Apr 2011 |
Study | Technical and financial study started | | | Consultant | Transaction advisory services contract awarded to Fichtner Consulting EngineersFichtner Consulting Engineers , HSBCHSBC and Norton RoseNorton Rose
|
| Dec 2011 |
Study | Technical and financial study completed
|
| 15 Jan 2012 |
DBO | EOI issued
|
| 15 Mar 2012 |
DBO | EOIs submitted
|
| Jun 2012 |
DBO | RFQ expected to be issued
|
| Q3 2012 |
DBO | RFP expected to be issued
|
| 2015 |
Completion | Project expected to be completed
|
|
|