| Owner |
: |
Directorate of Military Works
|
| Location |
: |
Abu Dhabi, UAE
|
| Contract Type |
: |
Construction |
| Facility Type |
: |
Residential development |
| Capacity |
: |
built up area: 44,000 sq.m. 71 villas |
| Main Usage |
: |
Residential |
|
| Background |
The Directorate of Military Works plans to build zone B of the Officers' Housing Complex in the Officers' City in Abu Dhabi, UAE. The project will have a 44,000 sq.m. built up area and will consist of 71 villas with related infrastructure works, a mosque and a social center. Khatib and Alami Consolidated EngineeringKhatib and Alami Consolidated Engineering is the design consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| 2014 |
Completion | Project expected to be completed
|
|
| Latest Events |
In March 2012, the construction of the development started. In 2014, the project is expected to be completed. |
| Previous Events |
In January 2012, the main construction contract (including MEP works) was awarded to Nael General Contracting Company. In 2011, the ITB for the main construction contract was issued. |
| Scope of Work |
Construction of a 44,000 sq.m. development including: - 71 villas - a mosque - a social center - related infrastructure works |
| Contract Packages |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2011 |
Construction | ITB for the main construction contract issued
|
| Jan 2012 |
Construction | Main construction contract (including MEP works) awarded to Nael General Contracting Company
|
| Mar 2012 |
Construction | Construction of the villas started
|
| 2014 |
Completion | Project expected to be completed
|
|
|