| Background |
Sorouh Real Estate CompanySorouh Real Estate Company plans to develop Saraya Abu Dhabi a mixed use development project that will be located on Abu Dhabi Corniche. Saraya Abu Dhabi will cover up a build up area of 738,181 sq.m. and will consist of 31 towers, that will include residential and commercial buildings ranging from 10 to 40 stories and the project will include construction of hotels. The project will be completed in phases. The first phase will include infrastructure work, and phases 2 and 3 will include the construction of the towers. PTW is the design consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| 2015 |
Completion | Project expected to be completed
|
|
| Latest Events |
In March 2012, the construction of the towers was still ongoing. In 2015, the project is expected to be completed. |
| Previous Events |
In September 2011, the construction of the towers was ongoing. In December 2010, the infrastructure works were completed. In Q4 2008, the construction of the towers started. In December 2007, the infrastructure contract was awarded to Orascom Construction IndustriesOrascom Construction Industries . In July 2007, ITB for infrastructure contract was issued. In 2007, project was announced. |
| Scope of Work |
Construction of a 738,181 sq.m. mixed development including: - 31 towers (residential and commercial) ranging from 10 to 40 stories - Hotels Infrastructure including roads, bridges, water, sewage, electrical and telecommunication networks. |
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2007 |
Announcement | Project announced
|
| Jul 2007 |
Construction | ITB for infrasturcture contract issued
|
| Dec 2007 |
Construction | Infratsructure contract awarded to Orascom Construction IndustriesOrascom Construction Industries
|
| Q4 2008 |
Construction | Construction started
|
| Dec 2010 |
Completion | Infrastructure works completed
|
| 2015 |
Completion | Project expected to be completed
|
|
|