| Also Known As |
: |
Suwwa Island |
| Country |
: |
UAE |
| Project Value |
: |
USD 3,000,000,000 Estimated |
| Sector |
: |
Real Estate | Mixed Development |
|
Consultants |
: |
Aedas
(Design) |
Goettsch Partners
(Design) |
Martha Schwartz
(Landscape) |
|
Contractor |
: |
Al Naboodah Contracting Company
(Infrastructure) |
| Profile Type |
: |
Contract Project
|
| Associated Projects |
: |
Contract (4) | Related Projects (2) |
|
Phase: Construction - Execution
|
|
Completion: 2014
|
|
|
|
| Background |
MubadalaMubadala plans to develop phase 1 of Sowwah Island, a mixed development located between Reem Island and Mina area, Abu Dhabi. Phase 1 will spread over an area of 1.1. million sq.m. and will include 5 major components: Sowwah Square, Abu Dhabi Securities Exchange, Rosewood Abu Dhabi, Four Seasons Hotel, Viceroy Abu Dhabi and Cleveland Clinic Abu Dhabi. The Cleveland Clinic will include a hospital with a 360 beds. The Sowwah Square will consist of 450,000 sq.m. area for the Abu Dhabi Securities Exchange Headquarter, 4 office towers, 2 hotels : "Rosewood Abu Dhabi" and "Four Seasons Hotel ", conference facilities, and retail and dining spaces. The project involves the construction of 13 bridges that will link Sowwah Island to its neighboring areas. The Sowwah Island is part of the Abu Dhabi's plan 2030. Martha Schwartz is the landscaping consultant, Goettsch Partners is the design consultant for Sowwah Square, and Aedas is the design consultant for the Cleveland Clinic. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q4 2012 |
Completion | Rosewood hotel expected to be completed | | H2 2013 | Completion | Sowwah square expected to be completed | | Q4 2013 | Completion | Cleveland Clinic expected to be completed | | 2014 | Completion | Project expected to be completed
|
|
| Latest Events |
In April 2012, the construction of the project was ongoing. In Q4 2012, Rosewood hotel is expected to be completed. In H2 2013, Sowwah square is expected to be completed. In Q4 2013, Cleveland Clinic is expected to be completed. In 2014, the project (including Four Season Hotel) is expected to be completed. |
| Previous Events |
In June 2011, Abu Dhabi Securities Exchange Center (sowwah square) was completed. In March 2011, one office tower (sowwah square) was completed. In February 2011, the ITB for the main construction contract for the Four Seasons Hotel was issued. In June 2010, the enabling works contract was awarded. MubadalaMubadala did not reveal the name of the contractor. In March 2010, the main construction contract for the Cleveland Clinic was awarded to the JV of Six ConstructSix Construct and Samsung Corporation. In January 2010, the main construction contract for the Rosewood Hotel was awarded to Arabian Construction CompanyArabian Construction Company and MEP works for Drake and Scull InternationalDrake and Scull International . In July 2008, the construction contract for the infrastructure works (including 4 bridges and 5 km of roads) was awarded to Al Naboodah ContractingAl Naboodah Contracting . In May 2008, the project was officially launched. In 2007, the EPC contract for Sowwah Square was awarded to Oger Abu DhabiOger Abu Dhabi In Q1 2007, the project was announced. |
| Scope of Work |
Construction of a mixed use development including: Sowwah Square (579,000 sq. m.) including: - Abu Dhabi Securities Exchange (ADX) - Two 37-floor office towers - Two 31-floor office towers - 23,000 sq. m. of retail outlets - 2 hotels (four season and rosewood) - Conference facilities - A 300-seat auditorium - A 5,200-car parking area Cleveland Clinic (500,000 sq. m.) including: - 360-bed full service hospital (including a laboratory, research centers, an education center, and related facilities) - Retail spaces - administration building - car park - Infrastructure facilities including 13 bridges and roads. |
| Contract Packages |
| Type |
Project Name |
Contract Value |
 |
Mubadala - Sowwah Island |
- |
 |
Mubadala - Sowwah Island - Phase 1 - Cleveland Clinic Abu Dhabi (CCAD) |
USD 1,300,000,000 |
 |
Mubadala - Sowwah Island - Phase 1 - Four Seasons Hotel |
USD 272,000,000 |
 |
Mubadala - Sowwah Island - Phase 1 - Rosewood Hotel |
USD 218,000,000 |
 |
Mubadala - Sowwah Island - Phase 1 - Sowwah Square |
USD 1,000,000,000 |
|
| Related Projects |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| Q1 2007 |
Announcement | Project announced
|
| 2007 |
EPC | EPC contract for Sowwah Square awarded to Oger Abu DhabiOger Abu Dhabi
|
| May 2008 |
Planning | Project officially launched
|
| Jul 2008 |
Construction | Infrastructure contract awarded to Al Naboodah ContractingAl Naboodah Contracting Company
|
| Jan 2010 |
Construction | Main Construction contract for Rosewood Hotel awarded to Arabian Construction CompanyArabian Construction Company and MEP works to Drake and Scull InternationalDrake and Scull International
|
| Mar 2010 |
Construction | Main construction contract for the Cleveland Clinic awarded to the JV of Six ConstructSix Construct and Samsung Corporation
|
| Jun 2010 |
Construction | Enabling work contract awarded
|
| Feb 2011 |
Construction | ITB for the construction contract of the Four Seasons Hotel issued
|
| 31 Mar 2011 |
Construction | Bids for the main construction contract for the Four Seasons Hotel submitted
|
| Mar 2011 |
Completion | One office tower (sowwah square) completed
|
| Jun 2011 |
Completion | Abu Dhabi Securities Exchange Center (sowwah square) completed
|
| Q4 2012 |
Completion | Rosewood hotel expected to be completed
|
| H2 2013 |
Completion | Sowwah square expected to be completed
|
| Q4 2013 |
Completion | Cleveland Clinic expected to be completed
|
| 2014 |
Completion | Project expected to be completed
|
|
|
Key:
Master Project
Package Project
Contract Project
|
|
 |