| Owner |
: |
Dubai Properties GroupDubai Properties Group - UAE
|
| Location |
: |
Dubailand, Dubai, UAE
|
| Contract Type |
: |
Construction |
| Facility Type |
: |
Community development |
| Capacity |
: |
Built up area: 2.2 million sq.m. |
| Main Usage |
: |
Community Development |
|
| Background |
Dubai Properties GroupDubai Properties Group plans to develop Remraam, a community development located next to the Arabian Ranches and Bawadi in Dubailand. The project will cover an area of 2.2 million sq.m. and will include low rise Arabian style buildings (5 to 7 storey buildings) arranged in 4 clusters, each within 2 sectors. It will also include a mall, parks, sports and recreational facilities. The project will be divided into 3 construction packages; package 1 covers 100 buildings, package 2 covers an area of 680,138 sq.m. and includes 46 buildings, 2 shopping centers, 2 mosques and 4 health clubs, and package 3 covers 25 buildings. Khatib and Alami Consolidated Engineering CompanyKhatib and Alami Consolidated Engineering Company is the design consultant. |
| Latest Events |
In December 2011, the project (package 2) was completed. |
| Previous Events |
In October 2011, Package 1 was completed. In April 2011, the infrastructure work were completed. In September 2010, the excavation and foundation works were completed, 72% of infrastructure works were completed and 77% of the superstructure was completed. In Q2 2010, package 3 was completed. In January 2010, 85% excavation works and 50% foundation works were completed. In August 2009, 90% of the excavation works were completed and 70% of the building foundation works were completed. In March 2009, 90% of the sewer, water, and drainage systems were completed, 65% of the infrastructure works were completed and the excavation works for the foundations of 82% of the buildings was completed. In January 2009, 60% of infrastructure works were completed by Emirates Roads Constructing Company (ERC). In June 2008, construction started. On 5 May 2008, Package 3 was launched and completely sold out. In April 2008, Package 2 (3,000 units) was launched. In Q1 2008, the construction contract for package 3 was awarded to Parkway International Contracting. In February 2008, infrastructure works for all phases started. In January 2008, grading work was completed. In November 2007, the construction contract including MEP works for packages 1 and 2 was awarded to Dubai Civil EngineeringDubai Civil Engineering . In November 2007, Phase 1 (2,090 units) was launched. In 2007, project was launched. |
| Scope of Work |
Construction of a 2.2 million sq.m. community development of 3 packages: - Package 1 covers 100 buildings - Package 2 covers 46 buildings, 2 shopping centers, 2 mosques and 4 health clubs - Package 3 covers 25 buildings |
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2007 |
Announcement | Project announced
|
| Nov 2007 |
Planning | Phase 1 launched | | | Construction | Construction contract including MEP works for package 1 and 2 awarded to Dubai Civil EngineeringDubai Civil Engineering
|
| Jan 2008 |
Construction | Ground works completed
|
| 01 Feb 2008 |
Planning | Package 3 launched
|
| Q1 2008 |
Construction | Construction contract for package 3 awarded to Parkway International Contracting
|
| Feb 2008 |
Construction | Infrastructure works started
|
| Apr 2008 |
Planning | Package 2 launched
|
| Q2 2010 |
Completion | Package 3 completed
|
| Jun 2010 |
Construction | Construction started
|
| Sep 2010 |
Construction | Foundation works completed
|
| Apr 2011 |
Construction | Infrastructure completed
|
| Oct 2011 |
Completion | Package 1 completed
|
| Dec 2011 |
Completion | Project completed
|
|
|