KGOC - Gas and Condensate Export System
Country : Saudi Arabia, Kuwait
Project Value : N/A
Sector : Oil and Gas | Transportation
Consultant : Penspen International Limited (PMS)
Contractor : Technip Abu Dhabi (EPC)
Profile Type :  Standalone Project
Phase:
EPC - Execution
Completion: Q2 2014
 
 
Owner : Kuwait Gulf Oil CompanyKuwait Gulf Oil CompanyLoading... - Kuwait
Location :
From 
Saudi Arabia
To 
Al Ahmadi, Kuwait
Contract Type : EPC - Engineering, Procurement, Construction
Facility Type : Export Pipelines
Capacity : 12 inch 
110 Km long
Background Kuwait Gulf Oil CompanyKuwait Gulf Oil CompanyLoading... (KGOCKGOCLoading...) plans to build a gas and condensate export system (GCES) on onshore and offshore locations between Saudi Arabia and Kuwait.

The project aims at delivering a combination of lean gas, condensate and sour gas from Al Khafji Joint OperationsAl Khafji Joint OperationsLoading... (KJOKJOLoading...) facilities in Saudi Arabia to KOCKOCLoading...'s tie-in intermediate slug catcher in Mina Al Ahmadi.

The project will help KOCKOCLoading... and KJOKJOLoading... reach their goal of flaring no more than 1% of produced natural gas.

Penspen is the PMS.
Expected Events
Schedule Contract Phase/Phase Description
Q2 2014 CompletionProject expected to be completed
Latest Events In May 2012, engineering works were ongoing.

In Q2 2014, the project is expected to be completed.
Previous Events In March 2012, Penspen was awarded the PMS contract. Penspen will also manage the EPC contractor.

In February 2012, the EPC contract was awarded to TechnipTechnipLoading... and engineering work started.

In 2011, the tendering and bidding process for the EPC contract was launched.
Scope of Work Construction of a 12 inch, 110 Km long pipeline, with 4 Km onshore and 47 Km offshore in Saudi Arabia, and 59 Km onshore in Kuwait.

Project Schedule

ScheduleContract Phase/PhaseDescription
2011 EPCTendering and bidding process launched
Feb 2012 EPCContract awarded to TechnipTechnipLoading...
 EPCEngineering work started
Mar 2012 PMCPMS contract awarded to Penspen
Q2 2014 CompletionProject expected to be completed
 
Kuwait Gulf Oil Company Building, Al Ahmadi Area, P.O. Box 9919, Kuwait City 61010, Kuwait, Al Assimah
Tel: +965 2398-0771,+965 2386-4387 | Fax: +965 2398-4282,+965 2398-0883,+965 2398-4281 | Email: info@kgoc.com | Website: http://www.kgoc.com
  • Name: Ali Al Najdi
    Position: Head of Field Development and Facilities
    Tel: +965 2-386-4436
 
Al Yasat Tower, 3rd Floor, Office 303, Al Najda Street, P.O. Box 46562, Abu Dhabi, United Arab Emirates, Abu Dhabi
Tel: +971 2-679-2526 | Fax: +971 2-678-0913 | Email: uaemail@pensen.com
 
Technip Abu Dhabi
Contractor - EPC
Guardian Office Tower, 4th Street, Abu Dhabi Island Area, P.O. Box 7657, Abu Dhabi, United Arab Emirates, Abu Dhabi
Tel: +971 2-611-6000,+971 2-611-6100 | Fax: +971 2-611-6111 | Email: tpauhmarketing@technip.com | Website: www.technip.com/en/entities/middle-east
  • Name: Sadaf Khalid
    Position: Project Secretary
    Email sakhalid@technip.com
  • Name: Daniel Gelas
    Position: Project Manager
    Tel: +971 2-611-6862