The project aims at securing accommodations and infrastructure serving the offshore pipelines and early production facilities as part of the Upper Zakum field development.
Expected Events
Schedule
Contract Phase/Phase
Description
Q4 2012
EPC
Construction expected to start
Q3 2014
Completion
Project expected to be completed
Latest Events
In March 2012, the EPC contract was officially signed between ZadcoZadco and Al JaberAl Jaber and engineering works started.
In Q4 2012, construction works are expected to start.
In Q3 2014, the project is expected to be completed
Previous Events
In February 2012, the EPC contract was awarded to Al JaberAl Jaber.
In H2 2011, the tendering and bidding process for the EPC contract was launched.
Scope of Work
Work includes:
- Early civil and infrastructure works - Construction of accommodations and camps
Al Jaber Group Building, Street 7, Musafah Area, Petroleum Services Area, Plot 1 and 1A, P.O. Box 2175, Abu Dhabi, United Arab Emirates, Abu Dhabi Tel: +971 2-555-4300 | Fax: +971 2-555-3370 | Email: aljaber@aje.ae | Website: www.aljaber.com