| Owner |
: |
GPS Chemoil
|
| Shareholders |
: |
Chemoil - Singapore - 40.00 %
Gulf Petroleum Supplies - UAE - 60.00 %
|
| Location |
: |
Fujairah, UAE
|
| Contract Type |
: |
EPC - Engineering, Procurement, Construction |
| Facility Type |
: |
Oil Storage Terminal |
| Capacity |
: |
580,000 cu.m oil |
|
| Background |
GPS Chemoil plans to expand the oil storage terminal in Fujairah, U.A.E. The project will be executed in phases. This is phase 4 of the project and it aims at increasing the production capacity of the terminal by 580,000 cu.m of oil. JURONG International Consulting is the PMC for the overall project. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Jul 2012 |
Completion | Project expected to be completed
|
|
| Latest Events |
In January 2012, construction work was ongoing. In July 2012, the project is expected to be completed. |
| Previous Events |
In January 2011, construction work started. In October 2010, the EPC contract was awarded to Nico International Hydrospace, a subsidiary of Topaz Engineering CompanyTopaz Engineering Company . In September 2010, the PMC contract was awarded to JURONG International Consulting. In April 2007, Chemoil and Gulf Petrol Supplies signed the Joint Venture agreement to develop the project. |
| Scope of Work |
Expansion of a 580,000 cu.m oil storage terminal. |
| Financing Source |
In October 2010, GPSChemoil secured a USD 90 million loan from a consortium of banks in Abu Dhabi, Dubai and Singapore to finance phase 4 of the project. The multi-currency loan was structured through a combination of Islamic and conventional loan tranches, with HSBC Bank Middle East LimitedHSBC Bank Middle East Limited acting as the lead arranger. |
| Contract Packages |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| Apr 2007 |
Planning | Chemoil and GPS signed the JV agreement
|
| Sep 2010 |
PMC | Contract awarded to JURONG International Consulting
|
| Oct 2010 |
EPC | Contract awarded to Nico International Hydrospace
|
| Jan 2011 |
EPC | Construction work started
|
| Jul 2012 |
Completion | Project expected to be completed
|
|
|