| Country |
: |
UAE |
| Project Value |
: |
USD 1,000,000,000 |
| Sector |
: |
Real Estate | Mixed Development |
|
Consultant |
: |
Shankland Cox Limited - UAE
(Architect, Design & Supervision) |
|
PMC |
: |
Robert Matthew Johnson Marshall (RMJM)
|
|
Contractor |
: |
Al Fara'a General Contracting Company
(Construction - Phase 1 ) |
| Profile Type |
: |
Standalone Project
|
|
| On Hold
|
Last Activity: Design - Execution
|
|
Initial Completion: 2012
|
|
|
|
| Background |
Abu Dhabi National Exhibition CompanyAbu Dhabi National Exhibition Company (ADNEC) plans to build Al Ain Convention Center District, a business and residential micro-city built in Al Ain, Abu Dhabi. The project will spread over an area of 275,000 sq. m. and will include state-of-the-art convention center, a cultural center, hotels, a serviced apartment complex, and a multi-storey car park, a cluster of residential and commercial low-rise buildings within an integrated micro-city. Phase 1 of the project involves the extension of the existing wedding hall located on site and phase 2 includes the construction of the other parts of the project. Upon completion, 220,000 sq. m. will be available to investors. Robert Matthew Johnson Marshall (RMJM) is the PMC and Shankland Cox is the architect, design and supervision consultant. |
| Latest Events |
In March 2012, the project was still on hold and no expected date to resume work. In 2012, the project was expected to be completed. |
| Previous Events |
In 2011, the project was put on hold. In September 2010, phase 1 was completed. In Q3 2010, the design of phase 2 started. In April 2010, the construction contract of the phase 1 was awarded to the Al Fara'a General Contracting CompanyAl Fara'a General Contracting Company and construction started. In June 2008, the master plan was completed. In 2008, the project was announced. |
| Scope of Work |
Construction of a 275,000 sq. m. mixed development including: - A cultural center with a library (6,654 sq. m.) - A conference hall with 225 rooms (16,500 sq. m.) - A convention center (5,000 sq. m.) - A hotel - 5 residential buildings - 3 serviced apartment buildings - 12 commercial office buildings |
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2008 |
Planning | Project announced
|
| Jun 2008 |
Design | Masterplan completed
|
| Apr 2010 |
Construction | Contract of phase 1 awarded to Al Fara'a General Contracting CompanyAl Fara'a General Contracting Company | | | Construction | Construction of phase 1 started
|
| Q3 2010 |
Design | Design of phase 2 started
|
| Sep 2010 |
Completion | Phase 1 completed
|
| 2011 |
Construction | Project put on hold
|
| 2012 |
Completion | Project was expected to be completed
|
|
|
|
 |