| Country |
: |
Bahrain |
| Project Value |
: |
N/A |
| Sector |
: |
Real Estate | Community Development |
|
Consultants |
: |
Global Design Strategies
(Design) |
Sime Malak and Alssamoure Design
(Architect ) |
Skidmore Owings and Merrill (SOM)
(Architect) |
WS Atkins & Partners - Bahrain
(Design and Engineer) |
|
PMC |
: |
Turner International Middle East
|
|
Contractors |
: |
Royal Boskalis Westminster
(Dregding & Land Reclamation) |
Ahmed Mansoor Al A'ali Company
(Infrastructure) |
| Profile Type |
: |
Master Project
|
| Associated Projects |
: |
Contract (2) | Related Projects (4) |
|
Phase: Construction - Execution
|
|
Completion: Apr 2014
|
|
|
|
| Owner |
: |
Bahrain Bay DevelopmentBahrain Bay Development - Bahrain
|
| Location |
: |
Manama , Capital, Bahrain
|
| Contract Type |
: |
Construction |
| Facility Type |
: |
Community development |
| Capacity |
: |
68,000 sq.m. residential tower 48,017 sq.m. office tower 20,450 sq.m. basement Parking |
| Main Usage |
: |
Community Development |
|
| Background |
Bahrain Bay DevelopmentBahrain Bay Development plans to build phase 2 of Bahrain Bay, a community development located at the northeastern shore of Manama, Bahrain. Phase 2 includes the construction of anchor developments: Four Seasons Hotel, a 68,000 sq.m. area of 201 m. tall tower with 50 storeys, 263 rooms, and will include a 5 star spa and leisure facilities, a"Sky Pod" restaurant,a hi-tech business centre, a multi-use ballroom, a banqueting hall , and 4 dining outlets; and Arcapita headquarter, a 48,017 sq.m. office tower; a 20,450 sq.m. area of basement Parking Garage with 525 capacity car units; and a 2 level structure mosque with prayer spaces, rooms, open courtyard facing Mecca, and a 50m tall minaret adjacent to the Mosque. Skidmore Owings and Merrill (SOM) is the architect, Sime Malak and Alssamoure Design are the architect consultants for Arcapita headquarter, Artifex is the landscape design consultant for Four Seasons Hotel, AtkinsAtkins is the design and engineer consultant, and Turner International is the PMC. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Apr 2014 |
Completion | Project including Four Seasons Hotel expected to be completed
|
|
| Latest Events |
In December 2011, the construction works for the Four Seasons Hotel were still ongoing. In April 2014, the project including Four Seasons Hotel is expected to be completed. |
| Previous Events |
In November 2011, construction works of the Four Seasons Hotel started. In October 2011, the construction contract for the Four Seasons Hotel was awarded to Six Construct. In Q1 2011, the piling works of Four Seasons Hotel was completed. In September 2010, the Arcapita headquarter was completed. In January 2008, the USD 22 million infrastructure contract was awarded to Ahmed Mansoor Al A'ali CompanyAhmed Mansoor Al A'ali Company and work started. In 2008, the piling contract for the Four Seasons Hotel was awarded to Dutch Foundation Company. In December 2007, Salhia Real Estate Company (SREC) signed the land purchase agreement to develop a USD 125 million commercial and retail tower in the same district as Arcapita headquarters and Raffles City. In March 2007, Arcapita signed the LOI with Ajmera Group and Myfair Housing to develop a USD 150 million housing project in Bahrain Bay; and the USD160 million construction contract for the Arcapita headquarters was awarded to JV of Nass Contracting CompanyNass Contracting Company and Murray & Roberts Contractors Middle East. In 2007, the dredging and reclamation work was completed and construction started. In May 2006, the dredging and land reclamation contract was awarded to Netherlands' Royal Boskalis WestminsterRoyal Boskalis Westminster . In 2006, project was announced. |
| Scope of Work |
Construction of a community development including: - Four Seasons Hotel ( 68,000 sq.m. area of 201 m. tall tower with 50 storeys, 263 rooms, and will include a 5 star spa and leisure facilities, a"Sky Pod" restaurant,a hi-tech business centre, a multi-use ballroom, a banqueting hall , and 4 dining outlets). - Arcapita headquarter (48,017 sq.m. and will consist of an office tower; a 20,450 sq.m. area of basement Parking Garage with 525 capacity car units; and a 2 level structure mosque with prayer spaces, rooms, open courtyard facing Mecca, and a 50m tall minaret adjacent to the Mosque). |
| Financing Source |
Bahrain's Ahli Bank financed USD 150 million for the infrastructure works. |
| Contract Packages |
|
| Related Projects |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2006 |
Announcement | Project announced
|
| May 2006 |
Construction | Dredging and reclamation contract awarded to Royal Boskalis WestminsterRoyal Boskalis Westminster
|
| 14 Mar 2007 |
Construction | LOI signed with Ajmera Group and Myfair Housing
|
| May 2007 |
Construction | Contract for the Arcapita headquarters awarded to JV of Nass Contracting CompanyNass Contracting Company and Murray & Roberts Contractors Middle East
|
| 2007 |
Construction | Reclamation work completed and construction started
|
| Jan 2008 |
Construction | Infrastructure contract awarded to Ahmed Mansoor Al A'ali CompanyAhmed Mansoor Al A'ali Company
|
| 2008 |
Construction | Piling contract for the Four Seasons Hotel awarded to Dutch Foundation
|
| Sep 2010 |
Completion | Arcapita headquarters completed
|
| Q1 2011 |
Completion | Piling works for Four Seasons Hotel completed
|
| Oct 2011 |
Construction | Construction Contract for Four Seasons Hotel awarded to Six Construct
|
| Nov 2011 |
Construction | Construction works for the Four Seasons Hotel started
|
| Apr 2014 |
Completion | Project including Four Seasons Hotel expected to be completed
|
|
|
Key:
Master Project
Package Project
Contract Project
|
|
 |