In April 2005, the ITB for the EPC contract was issued.
Scope of Work
Construction of 567 MW power plant and 30 million g/d desalination plant including 3 GE frame FA gas turbines, 2 heat recovery boilers, 2 multi stage flash distillers and associated facilities.
Financing Source
In June 2006,Financial closure was reached.