The Société Tunisienne de l'Electricité et du Gaz plans to build a combined cycle power plant in Ghannouch, south of Tunisia.
The power plant will have a capacity of 400 MW.
The power plant will enhance STEG's generating capacity to meet the country's growing demand for electricity, while at the same time optimising and upgrading the overall productivity.
Latest Events
In March 2011, the project was completed.
Previous Events
In November 2008, the construction of the plant started.
On 26 June 2008, the EPC contract was awarded to Alstom Power Systems.
Scope of Work
Construction of a 400 MW combined cycle power plant