Connecting intelligence with intelligence

×

Projects Monitor 

Covering major construction projects in the Middle East
Updated: 15May12
 
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Process Plant (Package 2)
Country : UAE
Project Value : N/A
Sector : Oil and Gas | Exploration & Production, Processing & Separation
Consultant : Fluor Mideast Limited (FEED)
PMC : Fluor Mideast Limited
Contractor : Saipem - UAE (EPC)
Sub-Contractors : Target Engineering Construction Company (Civil and Building) |  ABB Saudi Arabia (Power and Automation Equipment)
Profile Type :  Contract Project
Associated Projects : Contract (10)
Phase:
EPC - Execution
Completion: Q1 2014
 
 
Owner : Jv of Abu Dhabi National Oil Company and Occidental Middle East Development Company
Shareholders : Abu Dhabi National Oil CompanyAbu Dhabi National Oil CompanyLoading... - UAE - 60.00 %
Occidental Oil and Gas InternationalOccidental Oil and Gas InternationalLoading... - United States - 40.00 %
Location :
Shah Field, Abu Dhabi, UAE
Development Type : BOO
Contract Type : EPC - Engineering, Procurement, Construction
Facility Type : Process Plant
Background The JV of Abu Dhabi National Oil CompanyAbu Dhabi National Oil CompanyLoading... (AdnocAdnocLoading...) and Occidental Petroleum CorporationOccidental Petroleum CorporationLoading... plans to construct a process plant at the Shah field, Abu Dhabi.

The process plant package is the second package of the Shah Sour Gas Field Development project.

Fluor CorporationFluor CorporationLoading... is the PMC and FEED study consultant.
Expected Events
Schedule Contract Phase/Phase Description
Q1 2014 CompletionProject expected to be completed
Latest Events In May 2012, construction of the units and trains was ongoing.

In Q1 2014, the project is expected to completed.
Previous Events In September 2011, construction of the units and trains and civil work started.

In July 2011, a USD 30 million power and automation equipment sub-contract was awarded to ABB.

In June 2011, site preparation was ongoing.

On 21 February 2011, a USD 56 million civil and building works sub-contract was awarded to Target Engineering and Construction.

On 19 January 2011, the BOO Developer contract was officially signed between ADNOCADNOCLoading... and Occidental Petroleum CorporationOccidental Petroleum CorporationLoading....

On 1 November 2010, ADNOCADNOCLoading... shortlisted ExxonMobilExxonMobilLoading..., Royal Dutch ShellRoyal Dutch ShellLoading... and Occidental Petroleum for the developer BOO contract.

In August 2010, engineering work started.

On 21 June 2010, the PMC contract overseeing the overall program was awarded to Fluor CorporationFluor CorporationLoading....

On 2 May 2010, the EPC contract was awarded to SaipemSaipemLoading....

In April 2010, ConocoPhillipsConocoPhillipsLoading... officially announced its withdrawal from the project JV.

On 21 March 2010, commercial bids for the EPC contract were submitted (delayed from 3 March 2010).

On 3 November 2009, technical bids for the EPC contract were submitted (delayed from 10 September 2009).

In the end of August 2009, contractors submitted their EOI for the PMC contract overseeing the overall project.

In May 2009, the ITB for the EPC contract was issued.

In March 2009, the FEED study was completed.
Scope of Work Construction of:

- 4 Acid Gas Removal Units (AGRU)
- 2 NGL recovery trains
- 2 Condensate hydrotreater trains
Contract Packages
Type Project Name Contract Value
ADNOC/Oxy - Sour Gas Fields Development - Shah Field USD 10,000,000,000
ADNOC - Sour Gas Fields Development - Shah Field - Liquid Sulphur Pipeline (Package 6) -
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Offsites & Utilities (Package 4) -
ADNOC/Oxy - Gasco - Sour Gas Fields Development - Shah Field - Sulphur Handling and Export Terminal (Package 8) USD 614,000,000
ADNOC/Oxy - Gasco - Sour Gas Fields Development - Shah Field - Sulphur Treatment Facilities at Habshan (Package 7A) USD 500,000,000
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Early Works (Package 9) USD 300,000,000
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Gas Gathering System (Package 1) USD 470,000,000
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Non Process Buildings (Package 10) USD 600,000,000
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Product Pipelines (Package 5) USD 196,000,000
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Sulphur Recovery Units (Package 3) USD 1,450,000,000
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Sulphur Treatment Facilities at Shah (Package 7B) USD 550,000,000
Project News
20-Jan-2011 Occidental to partner Adnoc in Shah gas project - Gulf News

Project Schedule

ScheduleContract Phase/PhaseDescription
Mar 2009 FEEDStudy completed
May 2009 EPCITB issued
Aug 2009 PMCEOI submitted
03 Nov 2009 EPCTechnical bids submitted
21 Mar 2010 EPCCommercial bids submitted
02 May 2010 EPCContract awarded to SaipemSaipemLoading...
 
Bidders Awarded
21 Jun 2010 PMCContract awarded to Fluor CorporationFluor CorporationLoading...
Aug 2010 EPCEngineering work started
01 Nov 2010 BOOCompanies shortlisted for the Developer BOO contract
19 Jan 2011 BOOContract officially signed between ADNOCADNOCLoading... and Occidental Petroleum CorporationOccidental Petroleum CorporationLoading...
21 Feb 2011 ConstructionCivil and building works sub-contract awarded to Target Engineering and Construction
Jul 2011 Supply & InstallationPower and automation equipment sub-contract awarded to ABB
Sep 2011 EPCCivil and construction works started
Q1 2014 CompletionProject expected to be completed

Project News

20-Jan-2011 Occidental to partner Adnoc in Shah gas project - Gulf News
 
Jv of Abu Dhabi National Oil Company and Occidental Middle East Development Company
Owner 
Occidental Towers, 4th Street, Muroor Area, P.O. Box 73243, Abu Dhabi, United Arab Emirates
Tel: +971 2-691-7200 | Fax: +971 2-645-0395
  • Name: Nicola Nansour
    Position: Senior Executive Assistant
    Email nicola_nansour@oxy.com
  • Name: John Newbery
    Position: Business Development Director
Abu Dhabi National Oil Company Building, Corniche Street, P.O. Box 898, Abu Dhabi, United Arab Emirates
Tel: +971 2-602-0000 | Fax: +971 2-602-3389 | Email: info@adnoc.ae | Website: http://www.adnoc.ae
  • Name: Abdullah Al Suweidi
    Position: Onshore Division Commercial Manager
    Tel: +971 2-602-3781
 
Fluor Mideast Limited
Consultant - FEED
Al Obaidly Tower 5, 1st, 2nd, 14th and 15th Floor, Al Istiqlal Street, Khalidiya Area, P.O. Box 46858, Abu Dhabi, United Arab Emirates, Abu Dhabi
Tel: +971 2-617-2700 | Fax: +971 2-631-1660
 
Saipem - UAE
Contractor - EPC
BM Tower 1, 9th - 19th Floor, Al Ittihad Street, Al Nahda Area, P.O. Box 1802, Sharjah, United Arab Emirates, Sharjah
Tel: +971 6-593-7777 | Fax: +971 6-537-0051
  • Name: Alecio Testa
    Position: Project Manager
    Tel: +971 2-698-9898
 
Al Obaidly Tower 5, 1st, 2nd, 14th and 15th Floor, Al Istiqlal Street, Khalidiya Area, P.O. Box 46858, Abu Dhabi, United Arab Emirates, Abu Dhabi
Tel: +971 2-617-2700 | Fax: +971 2-631-1660
 
Target Engineering Construction Company
Sub-Contractor - Civil and Building
NBQ Building, 5th, 6th, 7th, 10th, 12th, 13th and 18th Floor, Hamdan Street, Tourist Club Area, P.O. Box 960, Abu Dhabi, United Arab Emirates, Abu Dhabi
Tel: +971 2-671-4700 | Fax: +971 2-671-4800 | Email: mail@target.ae | Website: www.target.ae
  • Name: Lorenzo D'Ambrosio
    Position: Business Development Manager
 
ABB Saudi Arabia
Sub-Contractor - Power and Automation Equipment
ABB Saudi Arabia Building, Al Ahsa Street, Malaz Area, P.O. Box 325841, Riyadh 11371, Saudi Arabia, Riyadh
Tel: +966 1-476-2644 | Fax: +966 1-476-9622 | Email: info@sa.abb.com | Website: www.abb.com.sa
  • Name: Abdul Aziz El Agaily
    Position: Project Director
    Tel: +966 3-843-3404
Key:    Master Project    Package Project    Contract Project