| Country |
: |
UAE |
| Project Value |
: |
N/A |
| Sector |
: |
Oil and Gas | Exploration & Production, Processing & Separation |
|
Consultant |
: |
Fluor Mideast Limited
(FEED) |
|
PMC |
: |
Fluor Mideast Limited
|
|
Contractor |
: |
Saipem - UAE
(EPC) |
|
Sub-Contractors |
: |
Target Engineering Construction Company
(Civil and Building) |
ABB Saudi Arabia
(Power and Automation Equipment) |
| Profile Type |
: |
Contract Project
|
| Associated Projects |
: |
Contract (10) |
|
Phase: EPC - Execution
|
|
Completion: Q1 2014
|
|
|
|
| Background |
The JV of Abu Dhabi National Oil CompanyAbu Dhabi National Oil Company (AdnocAdnoc ) and Occidental Petroleum CorporationOccidental Petroleum Corporation plans to construct a process plant at the Shah field, Abu Dhabi. The process plant package is the second package of the Shah Sour Gas Field Development project. Fluor CorporationFluor Corporation is the PMC and FEED study consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q1 2014 |
Completion | Project expected to be completed
|
|
| Latest Events |
In May 2012, construction of the units and trains was ongoing. In Q1 2014, the project is expected to completed. |
| Previous Events |
In September 2011, construction of the units and trains and civil work started. In July 2011, a USD 30 million power and automation equipment sub-contract was awarded to ABB. In June 2011, site preparation was ongoing. On 21 February 2011, a USD 56 million civil and building works sub-contract was awarded to Target Engineering and Construction. On 19 January 2011, the BOO Developer contract was officially signed between ADNOCADNOC and Occidental Petroleum CorporationOccidental Petroleum Corporation . On 1 November 2010, ADNOCADNOC shortlisted ExxonMobilExxonMobil , Royal Dutch ShellRoyal Dutch Shell and Occidental Petroleum for the developer BOO contract. In August 2010, engineering work started. On 21 June 2010, the PMC contract overseeing the overall program was awarded to Fluor CorporationFluor Corporation . On 2 May 2010, the EPC contract was awarded to SaipemSaipem . In April 2010, ConocoPhillipsConocoPhillips officially announced its withdrawal from the project JV. On 21 March 2010, commercial bids for the EPC contract were submitted (delayed from 3 March 2010). On 3 November 2009, technical bids for the EPC contract were submitted (delayed from 10 September 2009). In the end of August 2009, contractors submitted their EOI for the PMC contract overseeing the overall project. In May 2009, the ITB for the EPC contract was issued. In March 2009, the FEED study was completed. |
| Scope of Work |
Construction of: - 4 Acid Gas Removal Units (AGRU) - 2 NGL recovery trains - 2 Condensate hydrotreater trains |
| Contract Packages |
| Type |
Project Name |
Contract Value |
 |
ADNOC/Oxy - Sour Gas Fields Development - Shah Field |
USD 10,000,000,000 |
 |
ADNOC - Sour Gas Fields Development - Shah Field - Liquid Sulphur Pipeline (Package 6) |
- |
 |
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Offsites & Utilities (Package 4) |
- |
 |
ADNOC/Oxy - Gasco - Sour Gas Fields Development - Shah Field - Sulphur Handling and Export Terminal (Package 8) |
USD 614,000,000 |
 |
ADNOC/Oxy - Gasco - Sour Gas Fields Development - Shah Field - Sulphur Treatment Facilities at Habshan (Package 7A) |
USD 500,000,000 |
 |
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Early Works (Package 9) |
USD 300,000,000 |
 |
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Gas Gathering System (Package 1) |
USD 470,000,000 |
 |
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Non Process Buildings (Package 10) |
USD 600,000,000 |
 |
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Product Pipelines (Package 5) |
USD 196,000,000 |
 |
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Sulphur Recovery Units (Package 3) |
USD 1,450,000,000 |
 |
ADNOC/Oxy - Sour Gas Fields Development - Shah Field - Sulphur Treatment Facilities at Shah (Package 7B) |
USD 550,000,000 |
|