| Owner |
: |
Ministry of Oil - IraqMinistry of Oil - Iraq - Iraq
|
| Location |
: |
From South of Al Basra, Iraq
To West of Haditha, Al Anbar, Iraq
|
| Development Type |
: |
BOT |
| Facility Type |
: |
Oil and Gas Pipeline |
| Capacity |
: |
1.75 million bpd of oil 643 km pipeline |
|
| Background |
The Iraqi Ministry of OilIraqi Ministry of Oil plans to build an oil pipeline from Basra in the South of Iraq to Haditha, in the Western Anbar governorate in Iraq. This project is phase one of the Ministry's plan to rehabilitate and expand the country's oil and gas pipeline network. Phase one compromises a 1.75 million bpd pipeline from Basra in the South of Iraq to Haditha, in the Western Anbar governorate. At that point the pipeline will then split into two lines; one going westwards to the Syrian border and the other joining the northern export pipeline from Kirkuk to Ceyhan in Turkey. The project will also include a natural gas pipeline to supply the pumping stations in addition to a storage terminal and tanks in Basra, Haditha and Baiji, 200km from Baghdad. SNC LavalinSNC Lavalin is the engineering consultant manager. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| H1 2012 |
BOT | Tendering and bidding process expected to be launched
|
| 2013 |
Completion | Project expected to be completed
|
|
| Latest Events |
In November 2011, the project was under planning. In H1 2012, the tendering and bidding process for the BOT contract is expected to be launched. In 2013, the project is expected to be completed. |
| Previous Events |
On 10 May 2011, the engineering consultancy management contract was awarded to SNC LavalinSNC Lavalin . In April 2011, the project was launched. In 2007, the Iraqi Ministry of oil started planning for the project. |
| Scope of Work |
Construction of: -A 1.75 million bpd of oil pipeline -A natural gas pipeline -A storage terminal and tanks |
| Contract Packages |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2007 |
Planning | Planning for the project started
|
| Apr 2011 |
Announcement | Project launched
|
| 10 May 2011 |
Consultant | Engineering Consultancy Management contract awarded to SNC LavalinSNC Lavalin
|
| H1 2012 |
BOT | Tendering and bidding process expected to be launched
|
| 2013 |
Completion | Project expected to be completed
|
|
|