Updated: 24Feb12
 
ADFEC - Masdar Carbon Free City - Phase 1
Country : UAE
Project Value : USD 10,000,000,000 Estimated
Sector : Real Estate | Mixed Development
Consultants : Foster and Partners (Master Plan) |  Connell Mott MacDonald (Infrastructure ) |  WS Atkins & Partners Overseas - Dubai (Infrastructure Concept Design)
PMCs : CH2M Hill (Phase 1) |  Parsons Brinckerhoff Middle East
Contractors : Al Jaber Group - UAE (Infrastructure) |  Soletanche Bachy (Piling)
Profile Type :  Contract Project
Associated Projects : Contract (3)
Phase:
Construction - Execution
Completion: 2015
 
 
Owner : Abu Dhabi Future Energy CompanyAbu Dhabi Future Energy CompanyLoading... - UAE
Location :
Abu Dhabi, UAE
Contract Type : Construction
Facility Type : Mixed development
Capacity : Built up area: 130,000 sq.m.
Background The Abu Dhabi Future Energy CompanyAbu Dhabi Future Energy CompanyLoading... (ADFEC), also known as Masdar, plans to develop phase 1 of the Carbon Free City, an energy, science and technology green community in Abu Dhabi, between Khalifa City and Abu Dhabi International Airport.

Phase 1 of the project includes the construction of Masdar Institute of Science and Technology (MIST) and Masdar's headquarters. Phase 1 will occupy a 130,000 sq. m. area, which represents around 6% of the Masdar Carbon Free City.

Mott MacdonaldMott MacdonaldLoading... is the infrastructure consultant Foster and PartnersFoster and PartnersLoading... is the master plan consultant, Atkins is the infrastructure concept design consultant, and Parsons Brinckerhoff and CH2M HILL are the project management consultants.
Expected Events
Schedule Contract Phase/Phase Description
Q3 2012 ConstructionMIST expected to be completed
Q3 2013 CompletionSwiss village expected to be completed
2015 CompletionProject expected to be completed
Latest Events In February 2012, the bids for the main construction contract of masdar headquarter were under evaluation, design of the swiss village was ongoing and construction of phase 1B of MIST was ongoing.

In Q3 2012, the MIST is expected to be completed.

In Q3 2013, the Swiss village is expected to be completed (delayed from Q1 2012).

In 2015, the project is expected to be completed.
Previous Events In November 2011, Masdar headquarter was put on hold and phase 1A of MIST was completed.

In December 2010, the construction of phase 1 B of the MIST started.

In November 2010, the construction contract including the MEP works for phase 1B of the MIST was awarded to Arabian Construction CompanyArabian Construction CompanyLoading....

In 2010, the infrastructure works were completed.

In May 2009, Al JaberAl JaberLoading... started the enabling and foundation works for the Masdar Headquarters.

In January 2009, the USD 1.6 billion infrastructure contract was awarded to Al JaberAl JaberLoading... Group.

In June 2009, the infrastructure consultancy contract was awarded to Mott MacdonaldMott MacdonaldLoading....

In Q4 2008, the construction of phase 1 A of the MIST started.

In August 2008, the construction contract including MEP works for the phase 1A of the MIST was awarded to the joint venture of Al Ahmadiah ContractingAhmadiah ContractingLoading... and Trading Company and Hip Hing Construction Company.

In April 2008, the piling contract was awarded to Soletanche Bachy.

In June 2007, the master plan contract was awarded to Foster and PartnersFoster and PartnersLoading....

In 2006, the project was launched.
Scope of Work Construction of 46,000 sq. m. educational complex; Masdar Institute of Science and Technology (MIST) including:

- An institute (MIST)
- Research and laboratory facilities
- Residential units
- Retail outlets

Construction of 7-floor Masdar Headquarters including a conference center and related facilities.
Financing Source In September 2009, Masdar announced that it is seeking financing for phase 1 in the range of USD 300 million to USD 600 million over a period of seven years from Q1 2010.
Contract Packages
Type Project Name Contract Value
ADFEC - Masdar Carbon Free City USD 22,000,000,000
ADFEC - Masdar Carbon Free City - Phase 1 - Masdar Headquarters USD 300,000,000
ADFEC - Masdar Carbon Free City - Phase 1 - Masdar Institute of Science and Technology USD 500,000,000
ADFEC - Masdar Carbon Free City - Phase 1 - Swiss Village USD 200,000,000
Project News
17-Mar-2010 Masdar adapts its strategy to leaner times - The National
24-Apr-2009 Masdar Free Zone to Start Operations by June 2009 - Khaleej Times
10-Feb-2009 Jaber Energy wins $1.6bn Masdar contract - Emirates 24|7
01-May-2008 Mist joins hands with PI - Emirates 24|7
14-Feb-2008 Abu Dhabi starts work on $22b Zero-Carbon City - The Saudi Gazette
» More News

Project Schedule

ScheduleContract Phase/PhaseDescription
2006 AnnouncementProject launched
Jun 2007 DesignMaster plan contract awarded to Foster and PartnersFoster and PartnersLoading...
Apr 2008 ConstructionPiling contract awarded to Soletanche Bachy
Aug 2008 ConstructionConstruction contract including MEP works of phase 1 A of the MIST awarded to the JV of Al Ahmadiah ContractingAhmadiah ContractingLoading... and Trading Company and Hip Hing Construction Company
Q4 2008 ConstructionConstruction of phase 1 A of the MIST started
Jan 2009 ConstructionUSD 1.6 billion infrastructure contract awarded to Al JaberAl JaberLoading... Group
May 2009 ConstructionEnabling and foundation works for Masdar Headquarters started by Al JaberAl JaberLoading... Group
Jun 2009 ConsultantInfrastructure consultancy contract awarded to Mott MacdonaldMott MacdonaldLoading....
2010 CompletionInfrastructure works completed
Nov 2010 ConstructionConstruction contract including MEP works of phase 1 B of the MIST awarded to Arabian Construction CompanyArabian Construction CompanyLoading...
Dec 2010 ConstructionConstruction of phase 1 B of the MIST started
Oct 2011 CompletionConsturction of phase 1A (MIST) completed
Q3 2012 ConstructionMIST expected to be completed
Q3 2013 CompletionSwiss village expected to be completed
2015 CompletionProject expected to be completed

Project News

17-Mar-2010 Masdar adapts its strategy to leaner times - The National
24-Apr-2009 Masdar Free Zone to Start Operations by June 2009 - Khaleej Times
10-Feb-2009 Jaber Energy wins $1.6bn Masdar contract - Emirates 24|7
01-May-2008 Mist joins hands with PI - Emirates 24|7
14-Feb-2008 Abu Dhabi starts work on $22b Zero-Carbon City - The Saudi Gazette
 
Abu Dhabi Future Energy Company Building, Masdar City, Khalifa City A, P.O. Box 54115, Abu Dhabi, United Arab Emirates, Abu Dhabi
Tel: +971 2-653-3333 | Fax: +971 2-653-6002 | Email: info@masdar.ae | Website: http://www.masdar.ae
 
Connell Mott MacDonald
Consultant - Infrastructure
Abu Dhabi, P.O. Box 47094, Abu Dhabi, UAE
Tel: +971 2-445-7470 | Fax: +971 2-445-7490 | Email: mottmac@mottmac.co.ae | Website: http://www.conmottmac.com
 
WS Atkins & Partners Overseas - Dubai
Consultant - Infrastructure Concept Design
Al Rostomani Building, 3rd Floor, Khaled Bin Al Walid Street, Bur Dubai, P.O. Box 5620, Dubai, United Arab Emirates, Dubai
Tel: +971 4-405-9300 | Fax: +971 4-405-9301 | Email: office.dubai@atkinsglobal.com
 
Foster and Partners
Consultant - Master Plan
Al Saman Tower, 3rd floor, Hamdan Street, Abu Dhabi, P.O. Box 45715, Abu Dhabi, UAE
Tel: +971 2-417-1700 | Fax: +971 2-626-2544 | Email: info@fosterandpartners.com | Website: http://www.fosterandpartners.com
  • Name: David Nelson
    Position: Head of Design
 
Al Jaber Group - UAE
Contractor - Infrastructure
Al Jaber Group Building, Street 7, Musafah Area, Petroleum Services Area, Plot 1 and 1A, P.O. Box 2175, Abu Dhabi, United Arab Emirates, Abu Dhabi
Tel: +971 2-555-4300 | Fax: +971 2-555-3370 | Email: aljaber@aje.ae | Website: www.aljaber.com
  • Name: Kamal Ammar
    Position: Administration Manager
    Tel: +971 2-502-0694
    Email kamal.ammar@aje.ae
 
Soletanche Bachy
Contractor - Piling
European Business Center Building, 1st floor, Dubai Investment Park, P.O. Box 261130, Dubai, UAE
Tel: +971 4-813-5600 | Fax: +971 4-813-5601 | Website: www.bachy-soletanche.com
 
CH2M Hill
PMC - Phase 1
Abu Dhabi, P.O. Box 46844, Abu Dhabi, UAE
Tel: +971 2-513-3437 | Fax: +971 2-678-4145 | Website: http://www.ch2m.com
 
Abu Dhabi, Abu Dhabi, UAE
Tel: +971 2-652-9222 | Fax: +971 2-677-9772 | Email: pbpowerme@pbworld.com | Website: https://www.pbworld.com
Key:    Master Project    Package Project    Contract Project
Print
 
  • SEARCH MIDDLE EAST PROJECTS
 
 
 
 
Panel