Al Duqm airport will be executed in 3 packages. This project is package 2 which includes the construction of a runway and 2 taxiways. Package 1 includes the construction of a parking facility, roadways and utilities and package 3 includes the construction of the terminal buildings and other buildings on the site
In February 2012, the construction of the runway was still ongoing.
In November 2012, the project is expected to be completed.
Previous Events
In January 2011, the construction of the runway started.
In December 2010, the construction contract was awarded to Hanjin Heavy Industries and Construction.
On 13 June 2010, bidders submitted their proposals for the construction contract (delayed for the third time from 29 September 2009 due to changes in the design).
On 18 August 2009, the ITB for the main construction contract was issued.
On 22 September 2008, companies submitted their prequalification applications for the construction contract.
On 20 August 2008, the RFQ for the construction contract was issued.
Scope of Work
Construction of a 4 km long runway including:
- 2 taxiways - Parking apron for passenger aircraft - Facilities for 2 passenger boarding bridges - An air navigation and meteorology system - An airfield ground lighting system - A fuel farm - An apron fuel hydrant system