| Owner |
: |
Abdulsalam Al Rafi Group
|
| Location |
: |
Sheikh Zayed Road, Dubai, UAE
|
| Contract Type |
: |
Construction |
| Facility Type |
: |
Mixed development |
| Capacity |
: |
Built up area: 353,000 sq.m. Three 54-storey towers |
|
| Background |
Abdulsalam Al Rafi Group plans to built Burj Al Salam, a new mixed development located on Sheikh Zayed Road in Dubai, UAE. The development will have a 353,000 sq.m. built up area and will consist of three 54-storey towers; Tower 1 will be an office tower including commercial units, Tower 2 will consist of a Sheraton Hotel with 476 rooms and Tower 3 will be a residential tower including 510 units. The three towers will be linked with a 12-storey car parking having a 4-basement levels with a capacity for 2,100 cars. Erga Progress Engineering Consultants is the design and supervision consultant, LW Design Group is the interior design consultant and Chawla Architectural and Consulting is the lead and MEP consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Nov 2012 |
Completion | Project expected to be completed
|
|
| Latest Events |
In April 2012, the construction works were ongoing. In November 2012, the project is expected to be completed. |
| Previous Events |
In October 2011, the construction of the development was ongoing. In September 2010, a new construction contract was signed with Dubai Contracting CompanyDubai Contracting Company and construction resumed. In 2010, Design and Architecture Bureau (design consultant) withdrew form the project and was replaced by Erga Progress Engineering Consultants. In 2008, the project was put on hold. In 2007, the construction of the towers started. |
| Scope of Work |
Construction of a 353,000 sq.m. mixed development including: - Tower 1 (54 storeys): including commercial units - Tower 2 (54 storeys): a Sheraton Hotel with 476 rooms - Tower 3 (54 storeys): a residential tower including 510 units -12-storey car parking having a 4-basement levels with a capacity for 2,100 cars - 4-storey podium - Health club - Swimming pool - Gymnasium |
|
| Schedule | Contract Phase/Phase | Description |
| 2007 |
Construction | Construction started
|
| 2008 |
Construction | Project put on hold
|
| 2010 |
Design | Design and Architecture Bureau withdrew form the project | | | Design | Erga Progress Engineering Consultants appointed design and supervision consultant
|
| Sep 2010 |
Construction | New contract signed with Dubai Contracting CompanyDubai Contracting Company and construction resumed
|
| Nov 2012 |
Completion | Project expected to be completed
|
|
|