| Country |
: |
UAE |
| Project Value |
: |
USD 3,200,000,000 Estimated |
| Sector |
: |
Infrastructure | Airports |
|
Consultants |
: |
Kohn Pedersen Fox Associates
(Design) |
Skidmore Owings and Merrill (SOM)
(Master plan) |
|
PMC |
: |
Parsons International Limited
|
|
Contractor |
: |
NSCC International Limited
(Piling and excavation) |
| Profile Type |
: |
Contract Project
|
| Associated Projects |
: |
Contract (4) |
|
Phase: Construction - Selected
|
|
Completion: H1 2017
|
|
|
|
| Background |
The Abu Dhabi Airports CompanyAbu Dhabi Airports Company (ADACADAC ) plans to build the Midfield Terminal Complex in Abu Dhabi, UAE. The purpose of the project is to add 20 million people to the airport's passenger handling capacity and will allow for ultimate expansion to over 50 million passengers and more than 2 million tons of cargo each year. The project will include the construction of a 220,000 sq.m. terminal between the existing runway and a new second runway to be built 2 km to the north. The terminal will initially have over 30 gates, and will expand to over 80 gates to cope with anticipated growth. The project is part of Abu Dhabi's AirportAbu Dhabi's Airport expansion plan to increase passenger traffic from the current 7 million to above 40 million per year and cargo capacity to 2.5 million t/y. Skidmore Owings and Merrill (SOM) is the master plan consultant, Kohn Pederson Fox Associates is the design consultant and Parsons InternationalParsons International is the PMC. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Jun 2012 |
Construction | Main construction contract expected to be officially signed | | Q3 2012 | Construction | RFQ for airside civil works contract expected to be issued
|
| Q3 2012 |
CMS - Construction Management Services | Contract expected to be awarded
|
| Q3 2012 |
Construction | Construction expected to start
|
| H1 2017 |
Completion | Project expected to be completed
|
|
| Latest Events |
On 6 May 2012, ADACADAC selected the consortium of Consolidated Contractors Company, TAVTAV and Arabtec ConstructionArabtec Construction for the main construction contract. In May 2012, the bids for the CMS contract were under evaluation. In June 2012, the main construction contract is expected to be signed between ADACADAC and the consortium of Consolidated Contractors Company, TAVTAV and Arabtec ConstructionArabtec Construction . In Q3 2012, the CMS contract is expected to be awarded (delayed from March 2011) , the RFQ for the airside civil works contract is expected to be issued and construction of the midfield terminal complex is expected to start. In H1 2017, the project is expected to be completed. |
| Previous Events |
On 6 March 2012, the four shortlisted consortia submitted their final bids for the main construction contract. In February 2012, four consortiums were shortlisted for the main construction contract: Consortium of Arabian Construction Company, Samsung Corporation and Six Construct, Consortium of Bechtel, Enka and Al Jaber Group, Consortium of Consolidated Contractors Company, TAVTAV and Arabtec ConstructionArabtec Construction and Consortium of Hyundai Engineering and Construction, Kumho Engineering and Construction, China State Construction Engineering Corporation and Al Shafar General Contracting Company. In January 2012, the Abu Dhabi Government approved the Midfield Terminal project. On 13 November 2011, the bids for the main construction contract were submitted (delayed from 11 September 2011). In October 2011, the bids for the CMS contract were under evaluation. In June 2011, three companies backed out from their prequalified consortiums for the main construction contract: Taisei, Bouygues and Multiplex left their consortiums which were led by Al Naboodah, Arabian Construction Company and National Projects and Construction respectively. On 31 May 2011, SCADIASCADIA was dissolved and the planning and development of the Abu Dhabi International Airport Expansion was transferred to Abu Dhabi Airports CompanyAbu Dhabi Airports Company (ADACADAC ). In February 2011, the ITB for the main construction contract was issued. In January 2011, the prequalification process for the construction contract was completed. In December 2010, the excavation works were completed. In July 2010, the bids for the Construction Management Services (CMS) contract were under evaluation. In April 2010, the bids for the Construction Management Services (CMS) contract were submitted. The awarded company will work with the PMC and will manage the work of other sub-contractors and consultants. On 1 February 2010, bidders submitted their prequalification applications for the main construction contract. In December 2009, the RFQ for the main construction contract was issued. In Q3 2009, the BOT contract was canceled. The contract was expected to be re-tendered as a construction contract rather than a BOT contract. In May 2009, the prequalified contractors were selected. In February 2009, the piling and excavation works contract was awarded to National Services and Contracting Company (NSCC)National Services and Contracting Company (NSCC) . In January 2009, three companies were shortlisted for the BOT contract. The companies are Aeroports de Paris (ADP), Hochtief and TAVTAV . In November 2008, the ITB for the excavation construction contract was issued. The contract also covers finishing of the piling works. In June 2008, the design was completed. In Q4 2007, the ITB for the BOT pre-qualification was issued. In June 2006, the design contract was awarded to Kohn Pedersen Fox Associates. In October 2005, the ITB was issued for the design contract. In March 2005, the master plan was completed. |
| Scope of Work |
Construction of a 220,000 sq. m. terminal including: - 22 Km of conveyors - 10 reclaim carousels - 200 check-in counters - 65 contact gates - A multi-story car park - Retail and food outlets (27,500 sq. m.) - 23 hospitality lounges - A transit Hotel - A heritage and culture museum - Air-side developments - Landscaping |
| Contract Packages |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| Mar 2005 |
Design | Masterplan completed
|
| Oct 2005 |
Design | ITB issued
|
| Jun 2006 |
Design | Contract awarded to Kohn Pedersen Fox Associates
|
|
- Kohn Pedersen Fox Associates
|
|
| Q4 2007 |
BOT | Invitation to prequalify issued
|
| Jun 2008 |
Design | Design completed
|
| Nov 2008 |
Construction | ITB for the excavation works contract issued
|
| Jan 2009 |
BOT | 3 companies shortlisted for the contract
|
| Feb 2009 |
Construction | Piling and excavation contract awarded to NSCC
|
| May 2009 |
BOT | Prequalified contractors selected
|
| Q3 2009 |
BOT | Contract canceled
|
| Dec 2009 |
Construction | RFQ for main construction contract issued
|
| 01 Feb 2010 |
Construction | Bidders submitted their prequalification applications for main construction contract
|
| Apr 2010 |
CMS - Construction Management Services | Bidders submitted their proposals
|
| Dec 2010 |
Construction | Excavation works completed
|
| Jan 2011 |
Construction | Prequalification process completed
|
| Feb 2011 |
Construction | ITB for main construction contract issued
|
| 31 May 2011 |
Planning | SCADIASCADIA dissolved and planning and development of the Abu Dhabi International Airport Expansion transferred to ADACADAC
|
| 13 Nov 2011 |
Construction | Bids for main construction contract submitted
- Consortium of Al-Habtoor Leighton, Murray & Roberts Contractors and Hochtief
- Consortium of Arabian Construction Company - UAE, Samsung Corporation and Six Construct
- Consortium of Bechtel, Enka and Al Jaber Group
- Consortium of Consolidated Contractors Company , TAV and Arabtec Construction
- Consortium of Hyundai Engineering and Construction Company, Kumho Engineering and Construction, China State Construction Engineering Corporation and Al Naboodah Contracting Company
- Consortium of Larsen and Toubro Limited and National Projects and Construction
|
- Consortium of Al-Habtoor Leighton, Murray & Roberts Contractors and Hochtief
- Consortium of Arabian Construction Company - UAE, Samsung Corporation and Six Construct
- Consortium of Bechtel, Enka and Al Jaber Group
- Consortium of Consolidated Contractors Company , TAV and Arabtec Construction
- Consortium of Hyundai Engineering and Construction Company, Kumho Engineering and Construction, China State Construction Engineering Corporation and Al Naboodah Contracting Company
- Consortium of Larsen and Toubro Limited and National Projects and Construction
|
|
| 06 Mar 2012 |
Construction | Four shortlisted consortiums submitted their final bids for the main construction contract
|
| Jun 2012 |
Construction | Main construction contract expected to be officially signed
|
| Q3 2012 |
Construction | RFQ for airside civil works contract expected to be issued | | | CMS - Construction Management Services | Contract expected to be awarded | | | Construction | Construction expected to start
|
| H1 2017 |
Completion | Project expected to be completed
|
|
|