| Country |
: |
UAE |
| Project Value |
: |
USD 1,100,000,000 Estimated |
| Sector |
: |
Real Estate | Free Zones/Economic Zones, Commercial |
|
Consultants |
: |
Hellmuth Obata and Kassabaum Incorporated - UAE
(Master plan - phase 1) |
AECOM
(Design) |
|
Contractor |
: |
Dubai Civil Engineering
(Construction and MEP works - Phase 1) |
| Profile Type |
: |
Standalone Project
|
|
| Completed
|
|
Completion: Q1 2012
|
|
|
|
| Background |
TECOMTECOM plans to develop Dubai Studio CityDubai Studio City a commercial development that caters to the film, TV, radio and broadcasting industries on Dubailand, Dubai. The project will spread over an area of 2 million sq.m and will include 14 sound stages, 18 boutique studios and commercial offices. 330,000 sq.m will be allocated for back-lot outdoor shooting. The city will also have residential areas, cinema complexes and a film academy. The project will be developed in 3 phases. Phase I includes construction of the boutique studios, 3 sound stages, 4 office buildings, a 15- storey tower, a retail area, a warehouse and a workshop. Phase II includes the construction of the commercial and residential complexes, the remaining sound studios, cinema complex and film academy. HOKHOK is the master plan consultant for phase 1 and Maunsell Cansult is the design consultant and Al Hashemi is the architect conusltant. |
| Latest Events |
In Q1 2012, the project was completed. |
| Previous Events |
In September 2011, the construction of the project was on going and the expected date was not yet revealed. In April 2009, phase 1 was completed. In December 2007, the infrastructure works of phase I were completed and boutique studios were completed. June 2007, phase I construction has commenced the client has declined to release the name of the contractor involved and the date the contract was awarded. In 2006, master plan was completed. In 2005, the project was launched. |
| Scope of Work |
Construction of a 2 million sq.m. commercial development including: Phase I: construction of 18 boutique studios, four 6-storey office buildings, a 15-storey tower, a retail area, a warehouse and workshop. Phase II: construction of a commercial complex that includes 2 buildings (6,874 sq.m. each) and a tower (18,023 sq.m.) and the construction of residential complexes, sound studios, a cinema complex and a film academy. Installation of communication equipments and related facilities. Construction of Infrastructure that include, road, water, telecommunication and electrical networks. |
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| 2005 |
Announcement | Project announced
|
| 2006 |
Design | Master plan completed
|
| Jun 2007 |
Construction | Phase 1 commenced
|
| Dec 2007 |
Completion | Boutique studios completed | | | Completion | Infrastructure of phase 1 completed
|
| Apr 2009 |
Completion | Phase 1 of commercial complex completed
|
| Q1 2012 |
Completion | Project completed
|
|
|
|
 |