| Owner |
: |
Zakum Development CompanyZakum Development Company - UAE
|
| Location |
: |
Upper Zakum Field, Abu Dhabi, UAE
|
| Contract Type |
: |
EPC - Engineering, Procurement, Construction |
| Facility Type |
: |
Pipelines and Early Production Facilities |
| Capacity |
: |
100,000 bpd of oil |
|
| Background |
Zakum Development CompanyZakum Development Company (ZadcoZadco ) plans to develop phase 1 of its upper zakum full field development project in Abu Dhabi. The project includes the construction of offshore pipelines and cables to connect new production facilities on four artificial islands and the existing satellite platforms with central onshore facilities. Phase 1 aims to increase the capacity by 100,000 bpd of oil and the overall development aims to increase production capacity from 550,000 to 750,000 bpd by improving oil recovery at the field. TechnipTechnip is the FEED study consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q3 2012 |
EPC | Contract expected to be awarded
|
| 2014 |
Completion | Project expected to be completed
|
|
| Latest Events |
In May 2012, bids for the EPC contract were under evaluation. NPCC is the front runner. In Q3 2012, the EPC contract is expected to be awarded. In 2014, the project is expected to be completed. |
| Previous Events |
On 4 March 2012, commercial bids for the EPC contract were submitted (delayed from 22 August 2011). In December 2011, technical bids for the EPC contract were under evaluation and FEED study was ongoing. In the end of July 2011, technical bids for the EPC contract were submitted. On 16 May 2011, technical bids for the EPC contract were submitted. In the beginning of May 2011, companies were pre-qualified for the EPC contract and the ITB was issued. In January 2011, the EOIs for the EPC contract were submitted. In December 2010, the FEED study was ongoing. In October 2010, pre-qualification documents for the EPC contract were submitted. In Q2 2010, the FEED study contract was awarded to TechnipTechnip . |
| Scope of Work |
Work includes the construction of: - 227 Km subsea pipelines with diameter ranging between 8 inch and 42 inch - 125 Km cables - 5 riser platforms and flare structures - Brownfield work on existing facilities |
| Contract Packages |
|
|
| Schedule | Contract Phase/Phase | Description |
| Q2 2010 |
FEED | Contract awarded to TechnipTechnip
|
| Oct 2010 |
EPC | Pre-qualification documents submitted
|
| Jan 2011 |
EPC | EOIs submitted
|
| May 2011 |
EPC | ITB issued and companies pre-qualified
|
| 16 May 2011 |
EPC | Technical bids submitted
|
| Jul 2011 |
EPC | Amendments to the technical bids submitted
|
| Mar 2012 |
EPC | Commercial bids submitted
|
| Q3 2012 |
EPC | Contract expected to be awarded
|
| 2014 |
Completion | Project expected to be completed
|
|
|