| Also Known As |
: |
KADP, Jeddah Airport |
| Country |
: |
Saudi Arabia |
| Project Value |
: |
USD 4,500,000,000 Estimated |
| Sector |
: |
Infrastructure | Airports |
|
Consultant |
: |
Aeroports de Paris Ingenierie
(Design) |
|
PMC |
: |
Dar Al Handasah Shair and Partners
|
| Profile Type |
: |
Master Project
|
| Associated Projects |
: |
Contract (7) |
|
Phase: DB - Awarded
|
|
Completion: 2014
|
|
|
|
| Background |
The General Authority of Civil AviationGeneral Authority of Civil Aviation (GACA) plans to expand King Abdulaziz International AirportKing Abdulaziz International Airport (KAIA) in Jeddah, Saudi Arabia. The purpose of the project is to increase the airport's capacity from 15 million passengers per year to 30 million passengers per year. The KAIA Development Project (KADP) is developed in three phases at a cost of USD 11.3 billion. Phase 2 is expected to be completed in 2020 with a capacity of 50 million passengers per year and phase 3 is expected to be completed in 2035 with a capacity of 80 million passengers per year. The first phase of the airport expansion involves the overhaul and construction of 2 passenger terminals (north and south), the construction of a general aviation terminal, a desalination plant and other facilities. Aeroports De Paris Ingenierie (ADPI) is the design consultant. Dar Al Handasah Shair and Partners is the PMC. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Aug 2013 |
Completion | Airfield facilities package expected to be completed | | Q1 2014 | Completion | Automated people mover expected to be completed | | 2014 | Completion | Project expected to be completed
|
|
| Latest Events |
In April 2012, the construction of the airfield facilities, the new terminal and the automated people mover was ongoing, the fuel oil terminal was under planning and the DB contract for the aircraft maintenance hangars was awarded to the Jv of TAV, Al Rajhi Holding and Al Habtoor Leighton. In August 2013, the airfield facilities package is expected to be completed. In Q1 2014, the automated people mover is expected to be completed. In 2014, the project is expected to be completed. |
| Previous Events |
In November 2011, the construction of the new terminal and the airfield facilities was ongoing. In May 2011, the DBO contract for the automated people mover was awarded to Bombardier. In November 2010, the new terminal and the infrastructure package were awarded to Saudi Binladin GroupSaudi Binladin Group . In May 2010, the general aviation terminal was completed. In Q4 2009, the Hajj terminal was completed. In October 2009, the west runway was completed. On 12 February 2009, the north and south terminals were completed. In November 2008, GACA signed a USD 57 million contract with Fraport AG to operate the airport. In August 2008, Aeroports De Paris Ingenierie (ADPI) signed a USD 137 million design contract for Phase 1 of the KAIA expansion program. In February 2008, the design for KADP phase 1 started. In January 2008, the construction works started. |
| Scope of Work |
Phase 1 comprises of: -Geo-technical investigation package -Topographic survey package - Site logistic package - Main designer package - Mass earth work package - General aviation package - Infra-structures / Utilities package - Main terminal building ( foundation / structural / finishes ) including bagging handling system and passenger bridges - Elevated roads / Interchanges and bridges ( landside ) - New aircrafts control tower - Artwork package - Landscaping works - Airside taxiways / Roads packages - Buildings relocated / Removed package - Deportee terminal package - Railway station - Multistory car park |
| Contract Packages |
| Type |
Project Name |
Contract Value |
 |
GACA - King Abdulaziz International Airport - Phase 1 - Aircraft Maintenance Hangars |
USD 800,000,000 |
 |
GACA - King Abdulaziz International Airport - Phase 1 - Airfield Facilities Upgrade |
USD 270,000,000 |
 |
GACA - King Abdulaziz International Airport - Phase 1 - Fuel Oil Terminal |
USD 3,000,000,000 |
 |
GACA - King Abdulaziz International Airport Development Project - Phase 1 - Automated People Mover |
USD 96,000,000 |
 |
GACA - King Abdulaziz International Airport Development Project - Phase 1 - General Aviation Terminal |
USD 70,000,000 |
 |
GACA - King Abdulaziz International Airport Development Project - Phase 1 - New Terminal |
- |
 |
GACA - King Abdulaziz International Airport Development Project - Phase 1- North & South Terminals |
USD 132,000,000 |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| Jan 2008 |
Construction | Construction works started
|
| Feb 2008 |
Design | Phase 1 design started
|
| Aug 2008 |
Design | Contract awarded to Aeroport de Paris (ADPI)
|
| Nov 2008 |
Planning | Contract signed with Fraport AG to operate the airport
|
| 12 Feb 2009 |
Completion | North and south terminals completed
|
| Oct 2009 |
Completion | West runway completed
|
| Q4 2009 |
Completion | Hajj Terminal completed
|
| May 2010 |
Completion | General aviation terminal completed
|
| Nov 2010 |
DB | New terminal contract awarded to Saudi Binladin GroupSaudi Binladin Group
|
| Feb 2011 |
DB | Construction of new terminal started
|
| May 2011 |
DBO | Automated people mover contract awarded to Bombardier
|
| 19 Apr 2012 |
DB | Aircraft maintenance hangars contract awarded to the Jv of TAV, Al Rajhi Holding and Al Habtoor Leighton
|
| Aug 2013 |
Completion | Airfield facilities package expected to be completed
|
| Q1 2014 |
Completion | Automated people mover expected to be completed
|
| 2014 |
Completion | Project expected to be completed
|
|
|
Key:
Master Project
Package Project
Contract Project
|
|
 |