Takreer - Ruwais Carbon Black Plant
Country : UAE
Project Value : USD 500,000,000 Estimated
Sector : Oil and Gas | Processing & Separation, Storage
Consultants : Honeywell (Engineering, Design and Technology Provider) |  Bechtel Corporation (FEED)
PMC : WorleyParsons Engineering
Profile Type :  Standalone Project
Phase:
EPC - Bid Evaluation
Completion: Q1 2014
 
 
Owner : Abu Dhabi Oil Refining CompanyAbu Dhabi Oil Refining CompanyLoading... - UAE
Location :
Ruwais, Abu Dhabi, UAE
Contract Type : EPC - Engineering, Procurement, Construction
Facility Type : Carbon black plant, coker unit and hydrogen processing facilities
Background Abu Dhabi Oil Refining CompanyAbu Dhabi Oil Refining CompanyLoading... (TakreerTakreerLoading...) plans to construct a Carbon Black plant at its Ruwais Refining complex in Abu Dhabi, UAE.

The project also includes the construction of a coker unit and hydrogen processing facilities.

BechtelBechtelLoading... is the FEED study consultant.

WorleyParsonsWorleyParsonsLoading... is the PMC.

Honeywell International is the PDH technology provider.

Eurtecnica Contractors and Engineers is the carbon black technology provider and basic engineering design consultant.
Expected Events
Schedule Contract Phase/Phase Description
Jun 2012 EPCContract expected to be awarded
Q1 2014 CompletionProject expected to be completed
Latest Events In May 2012, bids for the EPC contract were under evaluation. Samsung Engineering was the frontrunner.

In June 2012, the EPC contract is expected to be awarded.

In Q1 2014, the project is expected to be completed.
Previous Events On 5 February 2012, commercial bids for the EPC contract were submitted (delayed from 5 January 2012).

In November 2011, the carbon black technology licensing and basic engineering design contracts were awarded to Eurotecnica Contractors and Engineers.

6 November 2011 was the technical bids submission deadline for the EPC contract (extended from 6 September 2011).

In October 2011, the tendering and bidding process for the EPC contract was slowed down over technology licenses contract issues.

On 11 July 2011, the ITB for the EPC contract was issued.

In the end of June 2011, the FEED study was completed.

In June 2011, the engineering, design and technology licensing contract for the Propane Dehydrogenation unit was awarded to Honeywell International.

In the beginning of May 2011, companies were pre-qualified for the EPC contract.

On 20 February 2011, companies submitted their EOIs for the EPC contract.

On 13 December 2010, the FEED study contract was awarded to BechtelBechtelLoading....

On 23 November 2010, the commercial bids for the FEED study contract were submitted.

On 19 September 2010, the technical bids for the FEED study contract were submitted (delayed from 2 September 2010).

On 2 September 2010, the PMC contract was awarded to WorleyParsonsWorleyParsonsLoading....

In August 2010, bids for the PMC contract were submitted.
Scope of Work Work includes the construction of:

- A carbon black plant
- A coker unit
- Propane Dehydrogenation unit
- Hydrogen processing facilities
- Spray coolers
- Storage and packing plant

Project Schedule

ScheduleContract Phase/PhaseDescription
Aug 2010 PMCBids submitted
02 Sep 2010 PMCContract awarded to WorleyParsonsWorleyParsonsLoading...
 
Prequalified Bidders Awarded
19 Sep 2010 FEEDTechnical bids submitted
23 Nov 2010 FEEDCommercial bids submitted
13 Dec 2010 FEEDContract awarded to BechtelBechtelLoading...
20 Feb 2011 EPCEOIs submitted
May 2011 EPCCompanies pre-qualified
 
Prequalified
Jun 2011 FEEDStudy completed
 DesignThe engineering, design and technology licensing contract for the Propane Dehydrogenation unit awarded to Honeywell International
11 Jul 2011 EPCITB issued
06 Sep 2011 EPCInitial technical bids submission deadline
06 Nov 2011 EPCExtended technical bids submission deadline
Nov 2011 DesignThe engineering, design and technology licensing contract for the carbon black plant awarded to Eurotecnica Contractors and Engineers
05 Feb 2012 EPCCommercial bids submitted
*Bidders list confidential
Jun 2012 EPCContract expected to be awarded
Q1 2014 CompletionProject expected to be completed
 
Al Khalifa Energy Complex, 11th-25th Floor, Khalifa Street, Corniche Area, P.O. Box 3593, Abu Dhabi, United Arab Emirates, Abu Dhabi
Tel: +971 2-602-7000 | Fax: +971 2-602-7001 | Email: publicrelations@takreer.com | Website: http://www.takreer.com
  • Name: Kamal Al Hashimi
    Position: Project Manager
    Tel: +971 2-602-7255
    Email alhashimi@takreer.com
  • Name: Saeed Al Mahri
    Position: Projects Procurement Manager
    Tel: +971 2-602-7066
    Email salmahri@takreer.com
 
Honeywell
Consultant - Engineering, Design and Technology Provider
Abu Dhabi, P.O. Box 45595, Abu Dhabi, UAE Tel: +971 2-443-2119 | Fax: +971 2-443-2536 | Website: http://www.honeywell.com
 
Bechtel Corporation
Consultant - FEED
H.E. Sh. Sultan Bin Surour Al Dhahiri Building, 15th floor, Al Salam Street, Abu Dhabi, Abu Dhabi, UAE
Tel: +971 2-699-8400 | Fax: +971 2-676-0899
 
Al Dhafir Tower, 13th Floor, Najda Street, Najda District, P.O. Box 44169, Abu Dhabi, United Arab Emirates, Abu Dhabi