DCAA - Al Maktoum International Airport - Cargo Terminal
Also Known As : JXB
Country : UAE
Project Value : USD 75,700,000
Sector : Infrastructure | Airports
PMC : Aeroports de Paris and Dar Al Handasah Shair and Partners
Contractor : Max Bogl
Profile Type :  Contract Project
Associated Projects : Contract (4)
Completed
Completion: Q4 2008
 
 
Owner : Al Maktoum International AirportAl Maktoum International AirportLoading... - UAE
Developer : Dubai Civil Aviation AuthorityDubai Civil Aviation AuthorityLoading... - UAE
Location :
Jebel Ali, Dubai, UAE
Contract Type : Construction
Facility Type : Cargo Terminal
Capacity : 41,000 sq.m. cargo terminal 
600,000 tpy handling capacity
Background Department of Civil AviationDepartment of Civil AviationLoading... (DCAADCAALoading...) plans to construct the Cargo Terminal package which is part of Al Maktoum International Airport (JXB) development to complement the existing Dubai International AirportDubai International AirportLoading....

The project is part of the JXB's phase 1 construction package, is a 41,000 sq. m. cargo terminal with an annual handling capacity of 600,000 tons.

JV of Dar Al Handasah Shair and PartnersDar Al Handasah Shair and PartnersLoading... and Aéroports de Paris (AdPi) is the PMC.
Latest Events In Q4 2008, the project was completed (it was originally expected in May 2008).

In September 2006, the construction contract was awarded to the JV of Arabtec ConstructionArabtec ConstructionLoading... and Max Bogl.
Scope of Work Construction of a 41,000 sq. m. cargo terminal (steel frame building) with a handling capacity of 600,000 tpy.
Financing Source DCAADCAALoading... is planning to raise USD1.6 billion through a sukuk (Islamic bond) issue to fund JXB's first construction phase.

A consortium of local and international banks will be formed to raise the cash.
Contract Packages
Type Project Name Contract Value
DCAA - Al Maktoum International Airport USD 8,000,000,000
DCAA - Al Maktoum International Airport - Central Utility Complexes USD 108,000,000
DCAA - Al Maktoum International Airport - First Fuel Farm USD 30,000,000
DCAA - Al Maktoum International Airport - First Runway Package USD 274,000,000
DCAA - Al Maktoum International Airport - Passenger Terminal and Control Tower USD 201,900,000
Project News
28-Jun-2010 Al Maktoum welcomes foreign cargo flights - Emirates 24|7
27-Jun-2010 RTA Completes Construction Works Of Enty/Exit Points Of Al Maktoum International Airport (27 June 2010) - WAM (Emirates News Agency)
27-Jun-2010 RTA completes construction works of entry/exit points of Al Maktoum International Airport - Press Release
03-Mar-2007 DLC's first cargo terminal unveiled at world air cargo event - Press Release
13-Feb-2007 Arabtec/Max tie-up wins Dh242m Dubai World Central deal - Gulf News
12-Feb-2007 Arabtec/Max Bogl JV receives two letters of acceptance from Department of Civil Aviation at Dh 242 Million - Press Release
02-Oct-2006 UAE: Arabtec project gets approval - Emirates Today
» More News

Project Schedule

ScheduleContract Phase/PhaseDescription
2004 PlanningStarted
Sep 2006 ConstructionContract awarded to the JV of Arabtec ConstructionArabtec ConstructionLoading... and Max Bogl
 
Bidders Awarded
  • JV of Al Habtoor Engineering and Murray & Roberts
  • JV of Arabtec Construction and Cypriot National Wheel J&P
  • Max Bogl
Q4 2008 CompletionProject completed

Project News

28-Jun-2010 Al Maktoum welcomes foreign cargo flights - Emirates 24|7
27-Jun-2010 RTA Completes Construction Works Of Enty/Exit Points Of Al Maktoum International Airport (27 June 2010) - WAM (Emirates News Agency)
27-Jun-2010 RTA completes construction works of entry/exit points of Al Maktoum International Airport - Press Release
03-Mar-2007 DLC's first cargo terminal unveiled at world air cargo event - Press Release
13-Feb-2007 Arabtec/Max tie-up wins Dh242m Dubai World Central deal - Gulf News
12-Feb-2007 Arabtec/Max Bogl JV receives two letters of acceptance from Department of Civil Aviation at Dh 242 Million - Press Release
02-Oct-2006 UAE: Arabtec project gets approval - Emirates Today
 
Al Maktoum International Airport, 1st Floor, Dubai World Central Area, P.O. Box 2525, Dubai, United Arab Emirates, Dubai
Tel: +971 4-216-1199,+971 4-504-5171 | Fax: +971 4-224-4383
  • Name: Khalifa Suhail Al Zaffin
    Position: Director, Engineering and Projects
    Tel: +971 4-216-6206
  • Name: Mounser Youssef
    Position: Senior Construction Project Manager
  • Name: Youssef Pirzada
    Position: Construction Project Manager
    Tel: +971 4-216-6208
 
Max Bogl
Contractor 
In Saeed Tower II, 2nd floor, Sheikh Zayed Road, Dubai, Dubai, UAE
Tel: +971 4-381-4400 | Fax: +971 4-321-8724 | Email: info@max-boegl.de | Website: http://www.max-boegl.de
  • Name: Adrian Louv
    Position: Project Manager
 
Aeroports de Paris and Dar Al Handasah Shair and Partners
PMC 
Dubai Tel: +961 1-790005 | Fax: +961 1-869026 | Email: info@dargroup.com | Website: http://www.dargroup.com
 
Dubai International Airport, Garhoud Area, P.O. Box 49888, Dubai, United Arab Emirates, Dubai
Tel: +971 4-216-2009 | Fax: +971 4-224-4502 | Email: dcaa@dcaa.gov.ae | Website: www.dcaa.gov.ae
Key:    Master Project    Package Project    Contract Project
Print
 
  • SEARCH MIDDLE EAST PROJECTS
 
 
 
 
Panel